Permit Information

TN0082376
Individual
Denial
Water Authority of Dickson County (WADC)
East Hickman Water Reclamation Facility
The Department proposes to deny this permit on the grounds that WADC has not demonstrated that greater than de minimis degradation of Exceptional Tennessee Waters is necessary to accommodate important economic or social development in the area of the discharge and has not demonstrated that less-degrading alternatives are not practicable.
M
M
09-DEC-2022
23-MAR-2022
09-JAN-2023
05-APR-2023
Lick Creek at mile 10.6
proposed advanced biological treatment of municipal wastewater with UV disinfection
2
08-JUL-2024 03:49PM

Other DWR permits at this site

No other permits found.

Permit Documents

View
LetterResolution No. 24-22 Regarding Water Authority of Dickson County's Application for a National Pollutant Discharge23-SEP-2024
EmailRCVD 03-MAY-24: email re: don't allow well water to be contaminated by Leonard & Norma Manor03-MAY-2024
EmailRCVD 24-MAR-24: email re: do not permit treated sewage in Lick Creek from Eric Clark24-MAR-2024
LetterREF 19-JAN-24: appeal WPC22-0027 before Tennessee Water Quality Control Board by Bill Penny19-JAN-2024
Notice of DeterminationNotice of Determination (NOD) 202321-DEC-2023
LetterRCVD 09-JUN-23: letter re: glad TDEC denied permit to WADC by Joanne Sadoski09-JUN-2023
LetterRCVD VIA EMAIL 05-JUN-23: letter re: denial is appropriate by Grace Stranch05-JUN-2023
AudioRCVD VIA EMAIL 05-JUN-23: audio re: drinking from Lick Creek by Donna Baker05-JUN-2023
LetterPublic Comments from Friends of Lick Creek in Opposition to the Proposed WADC Wastewater Discharge to Lick Creek05-JUN-2023
LetterRCVD VIA EMAIL 05-JUN-23: letter re: transcriptions of voicemails by multiple05-JUN-2023
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

no data found

Inspections

no data found

Wastewater Engineering Plans Review

21.0887ApprovedPERMTS12/3/20211/6/2022East Hickman Water Reclamation Facility
21.0480Review CompletePPDTNH6/3/2021-East Hickman Water Reclamation Facility