Site IDSiteLocationCityCountyEFO Name
5430Jasper STP1903 Industrial BoulevardJasperMarionChattanooga

Permit Information

TN0054585
Individual
Reissuance
Town of Jasper
Jasper STP
Treatment of municipal sewage
I
M
MW
24-MAR-2020
02-APR-2020
16-JUN-2020
01-AUG-2020
01-SEP-2020
31-AUG-2025
Tennessee River Mile 421.5 (Guntersville Lake)
treated municipal wastewater from Outfall 001
screen, comminutor, pump station, two-stage aerated lagoons, secondary clarifier (with sludge recycle) and chlorine contact chamber
4952
.78
15-APR-2024 10:55AM

Other DWR permits at this site

  • 1 - 3 of 3
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNB054585Jasper STP-BiosolidsActiveN/AChattanooga17-OCT-202217-OCT-202231-AUG-2024
TN0081353Jasper STP-IndividualInactiveMajorChattanooga01-NOV-201201-DEC-201231-AUG-2015
NR0801.121Town of Jasper-ARAPInactiveN/AChattanooga-18-DEC-200818-DEC-2009
  • 1 - 3 of 3

Permit Documents

View
ImageREF 19-APR-05: pix by TDEC.19-APR-2005
Notice of ViolationCompliance Evaluation Inspection May 200519-MAY-2005
Letter2nd copy of Jasper Show Cause19-MAY-2008
Inspection ReportJasper WENDB Data Entry Worksheet19-NOV-2009
ReportRenewal application07-FEB-2010
LetterRevised plan17-MAR-2011
LetterExtension request21-MAR-2011
ReportPOTW PTSARs14-APR-2011
ReportPermit modification07-JUN-2011
ReportREF 12-JUL-11: June 2011 DMR by Billy Simpson.12-JUL-2011
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

31-MAR-2024Pretreatment TAV and File ReviewIn Compliance
15-FEB-2023Pretreatment Compliance (oversight)In Compliance
13-JUL-2022Sanitary Sewer Overflow Non-SamplingIn Compliance
28-FEB-2022Pretreatment AuditOut of Compliance
05-JAN-2021Pretreatment TAV and File ReviewIn Compliance
04-FEB-2020Pretreatment Compliance (oversight)In Compliance
28-JAN-2020Compliance Sampling (CSI)Out of Compliance
22-JAN-2019Pretreatment TAV and File ReviewIn Compliance
20-MAR-2018Pretreatment Compliance (oversight)In Compliance
15-MAR-2017Pretreatment AuditIn Compliance

Wastewater Engineering Plans Review

21.0889RReview CompleteC&E ReviewTNH9/15/2023-Jasper CAP-ER
21.0889Review CompleteCAP/ERTNH1/25/2022-Jasper CAP-ER
15.0213ApprovedCAP/ERPJH4/6/20151/5/2016Corrective Action Plan/Engineering Report
23.0286ApprovedCDMJB6/5/20236/14/2023Hwy 283 and Hwy 28 Low Pressure Force Main
23.0210ApprovedCDTNH6/5/20236/20/2023Jasper Sewer Treatment Plant Modifications Phase 2
23.0209RApprovedCDTNH2/6/20242/23/2024Town of Jasper STP Modifications
23.0209ApprovedCDTNH6/5/20236/20/2023Jasper Sewer Treatment Plant Modifications Phase 1
23.0044ApprovedCDA. Bahour3/15/20233/17/2023Jasper Standard Specifications
22.0624ApprovedCDMJB11/29/202212/1/2022Jasper Middle School Lift Station
18.0932ApprovedCDA. Bahour1/8/20191/9/2019Ace Sewer Extension