5057Knoxville Utilities Board (KUB) - Loves Creek Wastewater Treatment Plant (STP)5760 Sandis LaneKnoxvilleKnoxKnoxville

Permit Information

TN0021822
Individual
Reissuance
Knoxville Utilities Board (KUB)
Loves Creek STP
treatment of municipal wastewater with activated sludge process
M
M
MW
23-MAY-2024
29-MAY-2024
25-JUN-2024
29-JUL-2024
01-DEC-2024
30-NOV-2029
Holston River Mile 5.0
treated municipal wastewater from Outfall 001
Activated sludge system using UV light disinfection with hypochlorite backup systems. Waste Activated Sludge (WAS) at the treatment plant is sent to the Kuwahee treatment plant through the sewer collection system.
4952
10.3
29-JUL-2024 08:14AM

Other DWR permits at this site

  • 1 - 2 of 2
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR056407KUB - Loves Creek WWTP-TMSPActiveN/AKnoxville19-JUL-202020-JUL-202030-JUN-2025
TNB021822KUB Loves Creek STP-BiosolidsInactiveN/AKnoxville---
  • 1 - 2 of 2

Permit Documents

View
SpreadsheetPTL documents24-JUL-2019
ReportRCVD VIA EMAIL 31-OCT-23: report re: annual wastewater compliance report by Kevin Keaton31-OCT-2023
ReportKUB LC SSO Mar 2103-MAY-2021
ReportKUB LC Bypass Mar 2103-MAY-2021
ReportApril 2020 PT SAR11-MAY-2020
ReportOct 2019 PT SAR12-NOV-2019
ReportApril 2019 PT SAR13-MAY-2019
ReportApril 2019 PT SAR13-MAY-2019
ReportOct 2018 PT SAR13-NOV-2018
ReportAPR 18 PT SAR 30-APR-2018
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

26-JUL-2023Compliance Eval (non-sampling) (CEI)In Compliance
29-APR-2022Compliance Eval (non-sampling) (CEI)In Compliance
11-AUG-2021Compliance Eval (non-sampling) (CEI)In Compliance
18-DEC-2019Compliance Eval (non-sampling) (CEI)In Compliance
13-DEC-2017Compliance Eval (non-sampling) (CEI)In Compliance
20-SEP-2016Compliance Eval (non-sampling) (CEI)In Compliance
06-AUG-2013Compliance Eval (non-sampling) (CEI)In Compliance
08-DEC-2008Compliance Eval (non-sampling) (CEI)Not Complete and/or Stable
14-NOV-2006Reconnaissance (RI)In Compliance

Wastewater Engineering Plans Review

24.0559ApprovedCDMJT7/24/229/4/20244525 Ernestine Drive LPS Extension
24.0626InactiveCDRGO8/24/148/26/2024Atoka Lane Sewer Shortline
23.0329ApprovedCDMJB6/22/20237/13/2023UGC - 204 Branch Lane
22.0780ApprovedCDCourtlandV3/13/20233/31/2023Holston Hills Pump Station Rehabilitation Project
23.0125ApprovedCDA. Bahour3/8/20233/17/2023KUB - Crystal Lake Drive 6915 - LPS
22.0519ApprovedCDA. Bahour3/3/20233/9/2023KUB - Pinnacle Dr 5305 - LPS
22.0462ApprovedCDTNH10/10/202210/12/2022Lyon's Creek Force Main Upsizing
21.0764ApprovedCDTNH10/11/202110/25/2021UGC - Elna Marie Dr 7035
20.0734ApprovedCDTNH12/10/20201/5/2021Wayland Road Pump Station
20.0661ApprovedCDMNU11/2/202011/30/20201544 Cliffside Lane