Site IDSiteLocationCityCountyEFO Name
5631Kingston Springs STP510 Valley DriveKingston SpringsCheathamNashville

Permit Information

TN0059790
Individual
Reissuance
Town of Kingston Springs
Kingston Springs STP
Treatment of municipal sewage using a facultative lagoon and disinfection using chlorination. Updated draft including new Ammonia limits.
I
M
MW
24-SEP-2020
07-OCT-2020
25-MAY-2021
29-JUN-2021
01-JUL-2021
31-MAY-2026
Harpeth River at mile 35.8
treated municipal wastewater from Outfall 001
STEP CS, 2 stage lagoon system with chlorination
4952
.25
08-OCT-2024 08:45AM

Other DWR permits at this site

  • 1 - 2 of 2
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNB059790Kingston Springs STP-BiosolidsInactiveN/ANashville---
TNR241963Town of Kingston SpringsTown of Kingston Springs, TN Wastewater Treatment Plant ImprovementsCGPInactiveN/ANashville-11-SEP-2017-
  • 1 - 2 of 2

Permit Documents

View
Letter1/19/2011 Alternatives analysis19-JAN-2011
Engineering Calculations17-0110 Kingston Springs Aeration Calculations15-FEB-2017
Letter17-0110 Kingston Springs Electrical Improvements Approval Letter27-FEB-2017
Letter17.0460 Consultant response to comment letter for plant upgrades09-AUG-2017
Engineering Report17.0460 Kingston Springs Engineering Report11-JUL-2017
Letter17.0460 Kingston Springs Engineering Report and Preliminary Plans Approval Letter14-AUG-2017
Letter17.0460 Kingston Springs Upgrades Incomplete Letter07-AUG-2017
Memo17.0543 Kingston Springs Final Plans and Spec Review Memo24-AUG-2017
Letter17.0543 Kingston Springs Plant Upgrade Approval Letter25-AUG-2017
Form20.0732 Fee Worksheet07-DEC-2020
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

13-APR-2021Compliance Eval (non-sampling) (CEI)Out of Compliance
21-JUN-2016Performance Audit (PAI)Out of Compliance
18-OCT-2012Compliance Sampling (CSI)NOV
28-MAR-2012Performance Audit (PAI)NOV
17-MAY-2006Performance Audit (PAI)NOV
17-JUN-2003Compliance Eval (non-sampling) (CEI)In Compliance

Wastewater Engineering Plans Review

22.0633PendingCDMJB10/5/202211/28/2022Willows of Kingston Springs
20.0732ApprovedCDMJB12/14/20201/12/2021Valley Drive Lift Station Upgrade
17.0543ApprovedSTPUPGRJAH8/16/20178/25/2017Contract 217 WWTP
17.0460ApprovedSTPUPGRJAH8/9/20178/14/2017Contract 217 Second Phase
17.0110ApprovedotherJAH2/3/20172/27/2017Contract 117 - Wastewater Treatment Plant Electrical Improvement
96.1357InactiveSTDSPEC-12/30/1996-STD SPECS