Site IDSiteLocationCityCountyEFO Name
93204Town of Huntingdon dba Huntingdon Water Treatment Plant175 Boundary StreetHuntingdonCarrollJackson

Permit Information

TN0026174
Individual
Reissuance
Town of Huntingdon
Barnett Street Wastewater Lagoon
Treatment of municipal sewage using a two-cell partial mix aerated treatment lagoon with disinfection and chlorine contact chamber. Modification revises WET and nutrient monitoring frequency consistent with requirements in TN0026166.
I
M
MW
01-AUG-2024
31-JUL-2024
05-AUG-2024
26-MAY-2020
06-JUL-2020
01-AUG-2020
31-JAN-2025
17-NOV-2020
Beaver Creek Mile 6.8
treated municipal wastewater via aerated lagoon from Outfall 001
lagoon system (exempt from 503) unless sludge is removed the lagoon
4952
.3
25-SEP-2024 04:29PM

Other DWR permits at this site

Permit Documents

View
EmailEmail to Mayor Smothers COIDC 202419-AUG-2024
LetterHuntingdon COIDC requirement letter 202416-AUG-2024
ApplicationUpdated Application with Email Clarifications01-AUG-2024
ApplicationRCVD VIA EMAIL 25-JUL-24: contact sheet, Form 2A, map, and flow schematic by Nina Smothers25-JUL-2024
LetterPT Audit Response15-JUL-2024
LetterRCVD VIA EMAIL 28-MAY-24: letter re: sig auth for Timothy Strnad by Nina Smothers28-MAY-2024
LetterPT Audit Letter20-MAY-2024
FormPT Audit Form and Supporting Documents20-MAY-2024
Notice of ViolationPT SAR NOV Failure to sample influent and effluent31-MAY-2023
Bio-monitoringHuntingdon Barnett Street Lagoon CBI 202314-APR-2023
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

I/IEFO CommunicationNotify EFO Prior to Beginning Plans App.4/12/2019Watch List54

Inspections

15-MAY-2024Pretreatment AuditIn Compliance
05-APR-2023Compliance Biomonitoring (CBI)In Compliance
14-DEC-2022Pretreatment TAV and File ReviewIn Compliance
28-MAR-2022Pretreatment Compliance (oversight)In Compliance
05-JAN-2021Pretreatment TAV and File ReviewIn Compliance
05-MAR-2020Pretreatment Compliance (oversight)In Compliance
24-JAN-2019Pretreatment AuditIn Compliance
05-APR-2018Compliance Eval (non-sampling) (CEI)In Compliance
05-APR-2018Sanitary Sewer Overflow Non-SamplingIn Compliance
10-JAN-2018Pretreatment TAV and File ReviewIn Compliance

Wastewater Engineering Plans Review