182795First Utility District of Carter County -Water System UpgradesVarious LocationsElizabethtonCarterJohnson CityView Map

Permit Information

NRS24.162
ARAP
Incomplete
First Utility District of Carter County
Water System Upgrades
10 utility line crossings. 1 crossing via bridge and 9 crossings via open-cut method
N/A
16-AUG-2024
09-SEP-2024
Unnamed Tributaries to Stoney Creek, Horselog and Blue Spring Branch
09-SEP-2024 10:30AM

Other DWR permits at this site

No other permits found.

Permit Documents

View
Notice of DeficiencyRAI09-SEP-2024
LetterAcknowledgment of Application27-AUG-2024
EmailAcknowledgment of Application Email27-AUG-2024
ApplicationApplication fee receipt27-AUG-2024
ApplicationApplication Package16-AUG-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections