Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5022City of Jefferson City, Tennessee - Wastewater Treatment Plant936 West Cherokee DriveJefferson CityJeffersonKnoxville

Permit Information

TN0021199
Individual
Reissuance
Jefferson City
Jefferson City STP
Treatment of municipal sewage via Sequencing Batch Reactors (SBRs) with chlorination and dechlorination. This reissue increases the treatment capacity from 1.0 to 2.0 MGD. The applicant determined that the 2.0 MGD facility will be able to maintain existing loads for antidegradation purposes. Any inherent degradation is justified.
M
M
MW
28-JUN-2024
27-MAR-2014
23-JUL-2024
27-AUG-2024
04-OCT-2024
01-JAN-2025
31-DEC-2029
Mossy Creek Embayment at mile 3.0 of Cherokee Lake
treated domestic wastewater from Outfall 001
Sequencing Batch Reactors (SBRs) with chlorination and dechlorination. Biosolids to landfill.
4952
2
04-OCT-2024 11:54PM

Other DWR permits at this site

  • 1 - 2 of 2
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNB021199Jefferson City-BiosolidsActiveN/AKnoxville25-JUL-201425-JUL-201430-APR-2019
TNR135682Jefferson City, TennesseeJefferson City Wastewater Treatment Plant ImprovementsCGPInactiveN/AKnoxville-30-NOV-201830-SEP-2026
  • 1 - 2 of 2

Permit Documents

View
FormQ4-Nitrogen-2416-DEC-2024
FormMOR-Novm-24 16-DEC-2024
FormQ4-biomonitoring-2416-DEC-2024
FormExtended Effluent-Novm-2416-DEC-2024
FormMOR-Oct.2413-NOV-2024
FormMOR-Sep-2414-OCT-2024
Letter24.0728 Plans Approval LTR 2024101111-OCT-2024
EmailPT PC/LL Preliminary Approval04-OCT-2024
PermitFinal permit; Issue 10/4/2404-OCT-2024
Monitoring ReportAugust 2024 Pace Lab Reports03-OCT-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

30-JUN-2023Compliance Eval (non-sampling) (CEI)In Compliance
12-MAY-2022Compliance Eval (non-sampling) (CEI)In Compliance
16-NOV-2020Compliance Eval (non-sampling) (CEI)In Compliance
21-JAN-2020Compliance Eval (non-sampling) (CEI)In Compliance
15-NOV-2018Compliance Eval (non-sampling) (CEI)In Compliance
03-NOV-2017Compliance AssistanceOut of Compliance
07-FEB-2017Compliance Biomonitoring (CBI)Out of Compliance
15-JUN-2015Compliance Biomonitoring (CBI)In Compliance
23-JUL-2013Compliance Eval (non-sampling) (CEI)In Compliance
30-SEP-2012Compliance Eval (non-sampling) (CEI)Notice of Deficiency

Wastewater Engineering Plans Review

22.0759ApprovedCDMNU12/13/20222/22/20232021 CDBG Sewer System Rehabilitation
22.0104ApprovedCDA. Bahour5/3/20225/6/2022Cherokee Bay Subdivision
21.0902ApprovedCDTNH12/16/20211/6/2022Greene Meadows Phase 5
21.0880ApprovedCDTNH12/2/202112/13/2021Greene Meadows Subdivision, Phase 4
21.0740ApprovedCDTNH11/29/202112/2/2021Jefferson City Industrial Sewer Extension
21.0571ApprovedCDMNU7/22/20218/18/2021Jefferson Park Subdivision
21.0356ApprovedCDA. Bahour5/25/20215/27/2021Greene Meadows Subdivision, Phase 3
20.0513ApprovedCDMJB10/15/202010/21/2020Founder's Point Subdivision
20.0579ApprovedCDA. Bahour9/22/202010/15/2020Jefferson City Standard Specifications
20.0097ApprovedCDMNU3/27/20203/30/2020Tennessee Valley Primary Care Sewer Line