171237Ridgeline/East Tennessee Gas pipeline projectNear Lewis LaneMontereyPutnamCookevilleView Map

Permit Information

NRS24.014
ARAP
Individual Permit
Incomplete
East Tennessee Natural Gas, LLC
Ridgeline Expansion Project
The Project consists of the installation of approximately 118 miles of 30-inch diameter pipeline and an approximately 4-mile 30-inch diameter header pipeline (collectively referred to as the Mainline), a 14,600-horsepower (HP) electric-powered compressor station with natural gas backup (Hartsville Compressor Station), an 8-megawatt (MW) solar power generation facility, installation of two new and modification of two existing metering and regulating (M&R) stations, and other appurtenant facilities
N/A
17-JUL-2024
12-AUG-2024
Multiple waterbodies including perennial steams. intermittent streams, and ponds/impoundments
12-AUG-2024 02:50PM

Other DWR permits at this site

No other permits found.

Permit Documents

View
LetterRequest for Additional Information12-AUG-2024
EmailRAI Email12-AUG-2024
Addendum2nd Supplemental Concurrence Letter - Trousdale17-JUL-2024
AddendumRidgeline Expansion Project Supplemental Concurrence Letter - Morgan/Roane 18-APR-2024
AddendumRidgeline Expansion Project Supplemental Concurrence Letter - Overton18-APR-2024
AddendumRidgeline Expansion Project Supplemental Concurrence Letter - Fentress18-APR-2024
EmailAdditional HD Concurrence Email18-APR-2024
AddendumRidgeline Expansion Project Supplemental Concurrence Letter - Cumberland18-APR-2024
EmailIncomplete - Request for Additional Information #126-MAR-2024
LetterCumberland Co. Aquatic Feature Concurrence 29-FEB-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections