5059Portland STP124 Morningside DrivePortlandSumnerNashville

Permit Information

TN0021865
Individual
Pending
When initially received, all applications are identified as "Pending." Pending status indicates that the application is in the que to be processed or that TDEC-DWR staff are reviewing the application (or Notice of Intent for general permits). Status "Pending" could be also interpreted as "work in progress."
City of Portland
Portland STP
Upgrading the treatment systems by adding 2 SBRs for a total of 4 SBRs to increase the capacity from 1.9 to 2.85 MGD. The new design will not increase loads of oxygen demanding pollutants and incidental degradation is justified by the applicant.
M
M
MW
28-JUN-2024
20-JUN-2019
06-AUG-2019
01-DEC-2019
01-JAN-2020
31-AUG-2024
Summers Branch at mile 8.6 to the Red River
treated municipal wastewater from Outfall 001
Sequencing Batch Reactor (SBR) activated sludge with chlorination, dechlorination, and post aeration. Sludge: was, imhoff, to land appl.
4952
2.85
01-JUL-2024 04:03PM

Other DWR permits at this site

  • 1 - 2 of 2
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR246722City of Portland, Tennessee2020 Wastewater Treatment Plant ExpansionCGPActiveN/ANashville-10-JUL-202330-SEP-2026
TNB021865Portland STP-BiosolidsIncompleteN/ANashville---
  • 1 - 2 of 2

Permit Documents

View
ApplicationRCVD VIA DOWNLOAD 28-JUN-24: contacts, Form 2A, map, flow diagram, DMR summary, and reports by Megan Heisler28-JUN-2024
Letter24.0227 Approval letter 2024053030-MAY-2024
Letter24.0289 Approval letter 2024052323-MAY-2024
Letter24.0325 Plans Approval LTR 2024052020-MAY-2024
LetterWPN 24.0148 Approval Letter03-MAY-2024
LetterWPN24.0160 Approval Letter 2024040101-APR-2024
EmailRCVD 26-MAR-24: email re: response to Notice of Application Due from Bryan Price26-MAR-2024
LetterWPN23.0747 Approval Letter 2024032626-MAR-2024
LetterPT Delegated Signatory21-MAR-2024
EmailResponse to resignation notice. Informing Portland they have 30 days to secure a new certified operator.11-MAR-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

I/I:Permit ViolationsCommissioner's OrderMoratorium on Connections see Item 8 under Order & Assessment Section (page 15).4/18/2017Active58

Inspections

17-JUN-2024Compliance Eval (non-sampling) (CEI)Pending
14-JUN-2023Pretreatment TAV and File ReviewIn Compliance
18-AUG-2022Compliance Eval (non-sampling) (CEI)Out of Compliance
07-JUL-2022Sanitary Sewer SystemIn Compliance
02-JUN-2022Pretreatment Compliance (oversight)In Compliance
25-MAY-2021Pretreatment AuditOut of Compliance
03-MAR-2021Follow-upOut of Compliance
07-JUL-2020Compliance Eval (non-sampling) (CEI)Out of Compliance
01-JUL-2020Sanitary Sewer Overflow Non-SamplingOut of Compliance
11-JUL-2019Pretreatment Compliance (oversight)Out of Compliance

Wastewater Engineering Plans Review

19.0252Review CompleteC&E ReviewSJH4/30/2019-Portland 2018 Annual CMOM Report
24.0325ApprovedCDRGO4/30/20245/20/2024Bracken Estates - Sanitary Sewer Plans
24.0289ApprovedCDMJB5/23/20245/23/2024Parkside Pointe SPS & Force main
24.0227ApprovedCDMJB4/1/20245/30/2024Parkside Pointe
24.0160ApprovedCDMJT3/1/20244/1/2024Sanitary Sewer Rehab of Portland Sudden Service
24.0148ApprovedCDJKM2/27/20245/3/2024Harbin Sandye Avenue - Sanitary Sewer Collection Plans
24.0015ApprovedCDTNH2/2/20242/5/2024N Harris Ln Sewer Extension
23.0747ApprovedCDTNH3/1/20243/26/2024HWY 52E No. 1 Lift Station Relocation
23.0629ApprovedCDTNH1/29/20241/29/2024Twin Lakes
23.0560ApprovedCDJKM2/26/20242/28/2024Richland Estates Subdivision – Sanitary Sewer Collection Plans