Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5091Jellico Utilities Authority292 London AvenueJellicoCampbellKnoxville

Permit Information

TN0022861
Individual
Reissuance
Jellico Utilities Authority
Jellico STP
Treatment of municipal sewage through oxidation ditch biological treatment preceded by mechanical screening and grit removal and followed by tertiary filtration, chlorination and dechlorination
I
M
MW
08-JUL-2024
10-JUL-2024
03-SEP-2024
04-OCT-2024
01-NOV-2024
31-OCT-2029
Elk Fork Creek mile 2.1
treated municipal wastewater from Outfall 001
Oxidation ditch biological treatment preceded by mechanical screening and grit removal and followed by tertiary filtration, chlorination and dechlorination.
4952
.75
09-OCT-2024 04:23PM

Other DWR permits at this site

  • 1 - 2 of 2
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
SOP-07075Jellico Electric and Water Systems - Rarity Mountain Phase I-SOPInactiveN/AKnoxville30-DEC-200901-FEB-201030-DEC-2014
TNB022861Jellico STP-BiosolidsInactiveN/AKnoxville---
  • 1 - 2 of 2

Permit Documents

View
LetterPT Pretreatment Program Required19-APR-2013
Notice of ViolationNOV dated 9-6-13 from 2013 CEI06-SEP-2013
Old PermitFinal Permit30-OCT-2014
MemoTrip Report to Jellico WTP and STP 05-DEC-2014
Letter2015 WW Operator Form04-SEP-2015
MemoTrip Report-Jan 201603-FEB-2016
EmailNetDMR Final Approval21-APR-2016
Form2016 Certified Oper Form04-AUG-2016
LetterCEI-Report-201628-NOV-2016
LetterSSO- Report 201619-DEC-2016
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

19-JAN-2007Reconnaissance (RI)In Compliance
27-JUL-2011Compliance Eval (non-sampling) (CEI)In Compliance
30-JUL-2013Compliance Eval (non-sampling) (CEI)NOV
14-AUG-2014Compliance Eval (non-sampling) (CEI)In Compliance
15-NOV-2016Compliance Eval (non-sampling) (CEI)In Compliance
01-MAY-2019Compliance Eval (non-sampling) (CEI)In Compliance
19-OCT-2021Compliance Eval (non-sampling) (CEI)In Compliance
17-APR-2024Compliance Eval (non-sampling) (CEI)Out of Compliance

Wastewater Engineering Plans Review

24.0659ApprovedCDTNH10/8/202410/23/20242023 ARC Sewer System Improvement Lift Station #1 Replacement
22.0555ApprovedCDMJB8/29/20229/27/20222020 ARC Sewer System Improvements - WWTP
14.0776ApprovedFMMNU10/15/201411/20/2014Branam Hill Road
14.0692ApprovedLINEMNU9/9/201411/13/2014East and West Davis Lane Sewer Line Extension
98.0016DeniedERWDM1/9/1998-JELLICO STP IMP AND I/I PROG./COMM. ORD.97-0112