Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
4883US Department of Energy, Oak Ridge National Laboratory (ORNL)1 Bethel Valley RoadOak RidgeRoaneKnoxville

Permit Information

TNR133329
CGP
Active
The University of Tennessee
Joint Institute for Neutron Sciences, ORNL, Office/Labratory
10-OCT-2008
10-OCT-2008
15-OCT-2008
30-SEP-2026
01-OCT-2021
White Oak Creek and tributaries, Unnamed tribs-Bear Creek
01-JUN-2023 01:51PM

Other DWR permits at this site

  • 1 - 9 of 9
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR136604Department of EnergyY-12 National Security ComplexCGPActiveN/AKnoxville-30-NOV-202130-SEP-2026
TNR132878Oak Ridge National Laboratory-CGPInactiveN/AKnoxville-14-DEC-2007-
TNR139975Spallation-CGPInactiveN/AKnoxville---
TNR190584Tennessee Valley Authority (TVA)Oak Ridge National Laboratory Construction of 161 & 13kV Trans LineCGPInactiveN/AKnoxville-23-JAN-200630-MAY-2010
TNR190525Tennessee Valley Authority (TVA)Oak Ridge National Laboratory Substation ConstructionCGPInactiveN/AKnoxville-17-JUN-200530-MAY-2010
SOP-23032U.S. Department of Energy (DOE)Oak Ridge National Laboratory (ORNL)SOPNewN/AKnoxville-01-MAY-202430-APR-2029
TN0002941U.S. Department of Energy (DOE)Oak Ridge National Laboratory (ORNL)IndividualReissuanceMajorKnoxville24-FEB-202301-MAR-202331-DEC-2023
SOP-22033US Department of Energy, Oak Ridge National LaboratoryGlobal Evaluation, Analysis, Research and Security ProjectSOPNewN/AKnoxville31-JAN-202301-FEB-202331-JAN-2028
TNR131450United States Department of Energy / Oak Ridge National Laboratory-CGPInactiveN/AKnoxville-19-JUL-2005-
  • 1 - 9 of 9

Permit Documents

There are no electronic documents available for publication on the DataViewer for the selected permit record.

Please contact our staff at Water.Permits@tn.gov for further information.

Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

no data found

CGP - Specific Information

Area Disturbed (acres)
3.3
Start Date
10/8/2008
Estimated End Date
4/10/2009
Streams
No
Wetlands
No
Exceptional TN Waters (ETW)
No
ETW Comment
-
Threatened and Endangered Species 1 mile radius
Yes
Threatened and Endangered Species 5 miles downstream
Yes
Unavailable Conditions Waters
No
Unavailable Conditions Waters Comment
-
EPSC Plan Findings
-

Contractors

Contractor 1
Rouse Construction Company
Start Date
-
Contractor 2
G.W. Wyatt Contracting
Start Date
-
Contractor 3
-
Start Date
-
Contractor 4
-
Start Date
-
Contractor 5
-
Start Date
-
Contractor 6
-
Start Date
-