Site IDSiteLocationCityCountyEFO Name
5133Cleveland Utilities STP1860 Old Lower River RoadClevelandBradleyChattanooga

Permit Information

TN0024121
Individual
Modification
Cleveland Utilities Authority (CUA)
Cleveland Utilities STP
Treatment of municipal sewage by ICEAS(TM) activated sludge process preceded by mechanical bar screening and grit removal and followed by disinfecting. Modification proposes changes associated with converting from chlorine disinfecting to disinfecting with ultraviolet light; Modification simultaneously updates the E. coli limit consistent with current state water quality standards.
M
M
MW
22-AUG-2024
26-AUG-2008
27-AUG-2024
03-SEP-2024
29-APR-2022
31-OCT-2023
30-APR-2027
03-OCT-2023
Hiwassee River at mile 15.4
treated municipal wastewater from Outfall 001
ICEAS(TM) activated sludge process preceded by mechanical bar screening and grit removal and followed by chlorination and dechlorination. Sludge is anaerobically digested, dewatered by centrifuge and land applied.
4952
21.6
27-NOV-2024 10:35AM

Other DWR permits at this site

  • 1 - 4 of 4
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
NR2101.017Cleveland UtilitiesCleveland Utilities Wastewater Support Building-2420 Guthrie Avenue NWARAPInactiveN/AChattanooga-23-MAR-202107-APR-2025
TNR058788Cleveland Utilities Authority (CUA)Cleveland Utilities STPTMSPNo ExposureN/AChattanooga---
TNB024121Cleveland Utilities Authority (CUA)-BiosolidsActiveN/AChattanooga27-SEP-201927-SEP-201915-AUG-2024
TNRX50143Cleveland Wastewater Treatment Facility-TMSPNo ExposureN/AChattanooga---
  • 1 - 4 of 4

Permit Documents

View
ApplicationRenewal Application01-OCT-2021
ApplicationRCVD VIA EMAIL 30-AUG-16: NPDES app by Ken Webb.30-AUG-2016
Corrective Action Plan24.0069 CAP/ER 31-JAN-2024
Draft PermitDraft Permit modification to change disinfection from TRC to UV radiation & update E. coli daily max limit04-SEP-2024
Draft PermitDraft Permit 2022 29-MAR-2022
Draft PermitDraft permit 2017 (for 2/28/2017 PN)10-MAR-2017
EmailPT Email Chain about AIRL13-SEP-2024
EmailPT Tech Eval LL26-AUG-2022
EmailEmail Re: NOV of 11-10-2010-NOV-2020
Email20.0401 request for information 2020071010-JUL-2020
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

Chronic OverflowsLetterWildwood Basin Manhole 71-65 (22-DEC-09); Manhole 4-11 (03-JUL-19), and Manhole 10-1AA (03-JUL-19)12/22/2009Active56

Inspections

20-DEC-2023Pretreatment TAV and File ReviewIn Compliance
07-NOV-2022Pretreatment Compliance (oversight)In Compliance
10-NOV-2021Pretreatment TAV and File ReviewIn Compliance
02-DEC-2020Pretreatment Compliance (oversight)In Compliance
20-NOV-2019Pretreatment AuditIn Compliance
10-JUL-2019Performance Audit (PAI)In Compliance
23-OCT-2018Pretreatment TAV and File ReviewIn Compliance
13-AUG-2018Compliance Biomonitoring (CBI)In Compliance
30-NOV-2017Pretreatment Compliance (oversight)In Compliance
18-OCT-2016Pretreatment TAV and File ReviewIn Compliance

Wastewater Engineering Plans Review

09.0411ApprovedIMPA. Bahour6/15/20097/16/2009Biosolids Conveyance System Installation
12.0116ApprovedREPLACA. Bahour3/12/20124/10/2012Centrifuge Replac. Hiwassee treatment plant
12.0455ApprovedREHABA. Bahour8/21/20129/6/2012SRF - Cleveland Utilities - Inflow & Infiltration Correction Project
13.0628RApprovedREHABPhil Simmo11/21/201312/5/2013SRF2013 Cleveland Rehabilitation Project
14.0646Approved-A. Bahour8/20/20149/16/2014Standby Generator
14.0693ApprovedLINEA. Bahour9/9/201410/6/2014Cleveland Chair Sewer Main Replacement Project
16.0423Approved-A. Bahour5/31/20166/21/2016Construction detail drawings- Standard Sewer Specifications
16.0661ApprovedFMJAH8/15/20168/23/2016Candies Creek
17.0043ApprovedIMPJAH2/17/20172/21/2017Contract 16-01 Peak Wastewater
17.0323ApprovedLINEA. Bahour6/23/20176/23/20179th Street