Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO NameGIS
176422Bolt Farm Treehouse, LLC600 English Cove RoadWhitwellMarionChattanoogaView Map

Permit Information

SOP-23017
SOP
Pending
When initially received, all applications are identified as "Pending." Pending status indicates that the application is in the que to be processed or that TDEC-DWR staff are reviewing the application (or Notice of Intent for general permits). Status "Pending" could be also interpreted as "work in progress."
Bolt Farm Treehouse, LLC
N/A
13-DEC-2024
13-SEP-2023
110 ft to series of unnamed tribs to Sequatchie River
13-DEC-2024 02:13PM

Other DWR permits at this site

No other permits found.

Permit Documents

View
LetterIncomplete Application Notification26-JUL-2023
EmailNotice of Incomplete Plans and No SOP Required or Cabins on LPP03-NOV-2023
EmailNotice that plans and permits are on hold without an engineer19-SEP-2023
ApplicationRCVD VIA EMAIL 13-AUG-23: SOP app packet by unsigned13-AUG-2023
ApplicationRCVD VIA EMAIL 13-DEC-24: drip app; supp'l narrative; Class V app; well map; well screening report; soil map; well screening report; well map; 19-Jul-23 SSDS const permit; soils map; 16-Sep-24 SSDS const permit; and prelim engineering report by Seth Bolt13-DEC-2024
ApplicationRCVD VIA EMAIL 28-JUN-23: SOP P&H app by Seth Bolt28-JUN-2023
LetterTDEC Letter to Owner on Regulatory Program Options05-MAY-2023