165041River Gorge Ranch (aka Aetna Mtn)195 Whiteside LoopGuildMarionChattanoogaView Map

Permit Information

TNR113846
CGP
Active
Thunder Enterprises
River Gorge Ranch Phase 1a
development for approx. 195 lots
27-MAY-2022
16-MAY-2022
03-JUN-2022
03-JUN-2022
30-SEP-2026
Nickajack Reservoir misc. tribs. Dry Creek, Running Water Creek
03-AUG-2023 11:58AM

Other DWR permits at this site

  • 1 - 3 of 3
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR113978Thunder EnterprisesRiver Gorge Ranch Phase 1BCGPActiveN/AChattanooga-02-OCT-2023-
TNR113740Thunder EnterprisesRiver Gorge Ranch (Aetna Mtn) CGPActiveN/AChattanooga-15-OCT-202130-SEP-2026
NRS23.011Thunder Enterprises, IncRiver Gorge Ranch Phase 1ARAPActiveMajorChattanooga16-OCT-202316-OCT-202315-OCT-2028
  • 1 - 3 of 3

Permit Documents

View
LetterRe: bank stabilization measures03-JUL-2024
Inspection ReportInspection Report13-MAY-2024
LetterNotice Letter18-APR-2024
LetterNOV response from RGR & Thunder Enterprises12-FEB-2024
LetterNOV-returned & re-sent regular mail09-FEB-2024
Notice of ViolationNOV for Thunder Enterprises, River Gorge Ranch 1A30-JAN-2024
Notice of Coverage (NOC)NOC with contractor 07-JUN-2022
Notice of Intent (NOI)Contractor Signed NOI & Certification Page07-JUN-2022
Notice of Coverage (NOC)NOC03-JUN-2022
SWPPPRevised SWPPP- only first page stored in WaterLog; for complete copy, see FileNet31-MAY-2022
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

07-MAY-2024Stormwater Construction Non-SamplingIn Compliance
23-JAN-2024Stormwater Construction Non-SamplingOut of Compliance

CGP - Specific Information

Area Disturbed (acres)
465.2
Start Date
-
Estimated End Date
-
Streams
Yes
Wetlands
Yes
Exceptional TN Waters (ETW)
No
ETW Comment
-
Threatened and Endangered Species 1 mile radius
Yes
Threatened and Endangered Species 5 miles downstream
Yes
Unavailable Conditions Waters
No
Unavailable Conditions Waters Comment
-
EPSC Plan Findings
-

Contractors

Contractor 1
Thunder Air Inc
Start Date
6/7/2022
Contractor 2
-
Start Date
-
Contractor 3
-
Start Date
-
Contractor 4
-
Start Date
-
Contractor 5
-
Start Date
-
Contractor 6
-
Start Date
-