5619Lick Creek Valley (Mosheim) Wastewater Treatment Plant420 Pottertown Road Mailing Address:1000 Main Street Mosheim, TN 37818..MosheimGreeneJohnson City

Permit Information

TN0059366
Individual
Modification
Town of Mosheim
Lick Creek Treatment Plant
Treatment of municipal sewage. This modification adds effluent monitoring and reporting for settleable solids and influent monitoring and reporting for CBOD5, TSS and flow that were inadvertently left out in the effluent limitations table on Part 1 of the permit issued on September 9, 2020.
I
M
MW
30-JAN-2020
19-FEB-2020
25-FEB-2020
11-JUN-2024
09-SEP-2020
01-OCT-2020
30-SEP-2025
01-SEP-2023
Lick Creek at mile 23.3
treated municipal wastewater
WAS to aerobic dig; some liq to lap site; some drybd to lap
4952
.975
10-JUN-2024 10:40AM

Other DWR permits at this site

Permit Documents

View
LetterREF 29-NOV-82: letter re: WLA for Mosheim STP by DJEy.29-NOV-1982
ReportREF 20-JUL-90: report re: stream assessment by Hari Akunuri.20-JUL-1990
ReportREF 27-APR-95: report re: stream assessment by Sherry Wang.27-APR-1995
MemoREF 07-APR-00: memo re: operator certification grade by Roger Lemasters.07-APR-2000
ReportREF 04-OCT-00: report re: planning standards for a proposed discharge by Maybelle Sparks.04-OCT-2000
ReportREF 23-OCT-00: report re: 303(d) permitting checklist by Maybelle Sparks.23-OCT-2000
ReportREF 31-AUG-05: report re: calculation of permit limits by TDEC.31-AUG-2005
FormAttachment No. 2-Mosheim WWTP-Johnson City EFO Phone Log24-NOV-2008
ApplicationREF 09-AUG-10: NPDES app by Billy Myers.09-AUG-2010
Public Notice DocumentREF 21-MAR-11: public notice by TDEC.21-MAR-2011
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

I/I:Overflows:PretreatmentEFO CommunicationChris Rhodes email dated 4-Apr-20194/4/2019Watch List80

Inspections

19-MAR-2024Pretreatment AuditOut of Compliance
02-MAR-2023Pretreatment TAV and File ReviewIn Compliance
30-JUN-2022Compliance AssistanceIn Compliance
11-MAR-2022Compliance AssistanceOut of Compliance
09-MAR-2022Pretreatment Compliance (oversight)Out of Compliance
25-FEB-2022Compliance AssistanceOut of Compliance
26-AUG-2021Sanitary Sewer Overflow Non-SamplingOut of Compliance
25-AUG-2021Compliance Eval (non-sampling) (CEI)Out of Compliance
30-JUL-2021Pretreatment TAV and File ReviewIn Compliance
22-SEP-2020Pretreatment Compliance (oversight)Out of Compliance

Wastewater Engineering Plans Review

22.0541ApprovedCDMNU8/23/202210/18/2022Sanitary Sewer Extension for Forest Glen Subdivision
22.0050ApprovedCDShannon Mc2/11/20222/16/2022Big G Project Sewer Extension
20.0405ApprovedCDAWJ8/7/20208/11/2020Mosheim 2019 CDBG Upgrade
24.0219Review CompletePERTNH3/27/20245/16/2024WW-PDC-01
12.0297ApprovedPERPhil Simmo6/26/20127/20/2012FIDP/RPC. Inc.
12.0107DeniedPERPhil Simmo3/1/2012-FIDP - Greene Co/US Nitrogen, LLC
15.0242ApprovedPSREHABMNU4/15/20156/1/2015Mosheim I/I Rehab CDBG
15.0341ApprovedSTPMODA. Bahour8/20/20158/20/2015Lick Creek Valley WWTP Improvements
15.0081ApprovedSTPMODMTS2/9/20156/9/2015FastTrack Improvements at Lick Creek Valley WWTP
24.0451Pending-TNH6/10/2024-WW-PDC-2 Biotower Media Removal