Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
34225Southeastern Provision, LLC1617 Helton RoadBean StationGraingerKnoxville

Permit Information

SOP-18010
SOP
Reissuance
Southeastern Provision, LLC
Temporary pump and haul of industrial process wastewater from a slaughter house operation to a POTW while solutions to problems with the SSDS operation are engineered.
N/A
X
PH
19-AUG-2020
19-FEB-2020
31-AUG-2020
28-FEB-2019
01-MAR-2019
30-JUN-2020
28-FEB-2019
NA
slaughterhouse processing wastewater
Pretreatment consists of dual screening and dissolved air floatation (DAF); Pump and haul consists of manually pumping into a tanker from the pump tank designed for dosing of the SSDS under normal conditions.
.01
26-JAN-2024 11:04AM

Other DWR permits at this site

  • 1 - 2 of 2
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
SOP-20019Southeastern Provision, LLC-SOPNewN/AKnoxville---
TNR058032Southeastern Provision, LLC-TMSPInactiveN/AKnoxville29-APR-200829-APR-200831-DEC-2006
  • 1 - 2 of 2

Permit Documents

View
PermitFinal Permit01-JUL-2023
ReportDrip Irrigation Design03-JUN-2021
ImagePhotos of STP Construction from Vernon Rowe with request for extension of PH permit06-MAY-2021
LetterRequest for Extension26-APR-2021
LetterC & E Advisement Letter; Final SOP Extension13-JUL-2020
Emaildistribution email for minor modified permit 202001-JUL-2020
PermitMinor modification to extend PH permit through June 30, 202130-JUN-2020
LetterPermitting Response Letter24-JUN-2020
ApplicationRenewal Application11-FEB-2020
EmailCover email with SOP renewal application11-FEB-2020
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

no data found

Inspections

no data found

Wastewater Engineering Plans Review

19.0584InactivePP-ERJCN9/12/2019-Southeastern Provision LLC Wastewater Management System Project