TN0021253
Individual
Reissuance
City of Church Hill
Church Hill POTW
Treatment of municipal sewage by extended aeration activated sludge (oxidation ditch) and ultraviolet light disinfection
M
M
MW
13-FEB-2024
31-JAN-2024
05-MAR-2024
16-APR-2024
17-MAY-2024
01-JUN-2024
31-MAY-2029
Holston River at mile 136.5
treated domestic, commercial, and industrial wastewaters from Outfall 001
treatment of municipal sewage
4952
2.5
09-JUL-2024 08:00AM

Other DWR permits at this site

Permit Documents

View
EmailPT Audit Responses 01-05 Reply30-AUG-2024
EmailPT Audit Response 05 Permits for Review23-AUG-2024
EmailPT Audit Response 04 Local Limits23-AUG-2024
EmailPT Audit Response 04 Reply Local Limits23-AUG-2024
AddendumChurch Hill WWTP NOV Response-Compliance and Pretreatment Audit Inspections Chart22-AUG-2024
Corrective Action PlanChurch Hill WWTP NOV Response-Compliance Inspection22-AUG-2024
EmailPT Audit Response 03 Questions16-AUG-2024
EmailPT Audit Response 02 Questions16-AUG-2024
Monitoring ReportCity of Church Hill July 2024 MOR 16-AUG-2024
EmailPT Audit Response 01 ERP16-AUG-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

Inspections

16-JUL-2024Pretreatment AuditOut of Compliance
11-JUN-2024Compliance Eval (non-sampling) (CEI)Out of Compliance
11-JUN-2024Sanitary Sewer Overflow Non-SamplingOut of Compliance
10-OCT-2023Pretreatment Follow-upIn Compliance
07-SEP-2023Pretreatment TAV and File ReviewIn Compliance
18-AUG-2022Pretreatment Compliance (oversight)Out of Compliance
23-MAR-2022Sanitary Sewer Overflow Non-SamplingOut of Compliance
23-MAR-2022Compliance Eval (non-sampling) (CEI)Out of Compliance
10-AUG-2021Pretreatment TAV and File ReviewOut of Compliance
18-SEP-2020Pretreatment Compliance (oversight)In Compliance

Wastewater Engineering Plans Review

20.0694ApprovedCDA. Bahour12/21/202012/22/2020City of Church Hill Island View Drive Sewerline Extension
18.0481ApprovedotherMNU7/16/20187/17/2018Deerfield Circle
17.0233ApprovedPSMNU5/5/20175/5/2017Greenland PS Upgrade
17.0120ApprovedPSMNU2/9/20172/17/2017Phipps Bend PS Valve Installation
16.0730ApprovedLPCSMNU9/7/20169/22/2016West Morgan Street
14.0757ApprovedSTPMODA. Bahour10/7/201411/12/2014Wastewater Treatment Plant Sludge Press
14.0192ApprovedLINEMNU4/7/20146/30/2014Carters Valley Sewer Extension
13.0282Review CompletePERJMS5/29/20137/3/20132013 CDBG - City of Church Hill WWTP Improvements
12.0480Review CompletePERJMS7/26/20128/16/2012CDBG-2012 - Church Hill Sewer System Improvements Project
14.0374InactiveSTPMODA. Bahour6/4/2014-Sludge Press Builiding and Sludge Press