Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
2109Hamilton County Water & Wastewater Treatment Authoritycounty-wideChattanoogaHamiltonChattanooga

Permit Information

SOP-89044
SOP
Reissuance
Hamilton County Water & Wastewater Treatment Authority (WWTA)
Municipal Satellite Collection System
Sewage collection system to Chattanooga interceptor sewer system and Moccasin Bend STP
N/A
M
CS
05-FEB-2024
22-JAN-2024
06-FEB-2024
09-APR-2024
01-APR-2019
01-AUG-2019
31-JUL-2024
TN River and tributaries; distances vary
No discharge allowed
Collection system
24-JUN-2024 09:35AM

Other DWR permits at this site

No other permits found.

Permit Documents

View
Report2023 Q4 & SSO reports12-JAN-2024
ReportQ2 & SSO reports14-JUL-2023
Report2023 1st Quarter Report14-APR-2023
ReportRevised 3rd Quarter Report13-OCT-2021
Report4th Quarter Report15-JAN-2021
Report3rd QTR Report14-OCT-2020
ReportFollow-up SSO Report12-FEB-2020
ReportUpdated SSO Report12-FEB-2020
ReportSSO Report Follow-Up27-DEC-2019
ReportSSO Report23-DEC-2019
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

Chronic OverflowsLetterLetter 12/18/201812/18/2018Active

Inspections

16-NOV-2023Sanitary Sewer SystemOut of Compliance
01-NOV-2018Sanitary Sewer Overflow Non-SamplingOut of Compliance
20-JUL-2017Compliance Evaluations (non-NPDES)Out of Compliance

Wastewater Engineering Plans Review

24.0200ApprovedCDTNH3/19/20245/16/2024West Brow Oval Pump Station Improvements (WWTA Project No.12-316, SWIG ID 2022-8571, Project WW-PDC-1
24.0188ApprovedCDMJB3/12/20245/7/2024Signal Mountain Phase 1 Infrastructure Improvements Project - SWIG 2022-8379
24.0010ApprovedCDMJB3/12/20243/13/2024Rhinehart Valley Phase 1 Forcemain Upgrades
23.0757ApprovedCDTNH12/5/202312/15/2023East Ridge Phase 4 Rehabilitation Project SWIG ID: 2022-8669
23.0551ApprovedCDMJT9/20/20239/26/2023EAST RIDGE PHASE 3 REHABILITATION PROJECT
23.0457ApprovedCDMJB9/18/202310/2/2023Dogwood Estates Subdivision
23.0306Review CompleteCDTNH6/14/2023-Soddy Daisy Sewer Rehabilitation
23.0110ApprovedCDA. Bahour6/9/20236/12/2023WWTA Standard Details and Specifications
22.0726ApprovedCDTNH11/28/202212/13/2022Rhinehart Valley Pump Station Pump Upgrade
22.0420ApprovedCDTNH7/25/20227/25/2022Soddy Daisy Industrial Park Pump Station and Storage Basin