Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO NameGIS
2276Town of Atoka Collection SystemTown-wide - Multiple Streets, Multiple SubdivisionsAtokaTiptonMemphisView Map

Permit Information

SOP-98007
SOP
Reissuance
Town of Atoka
Collection System
Operation of a satellite municipal sewage collection system, via interjurisdictional agreement with the City of Munford, consisting of gravity and low-pressure sewers serving 3,250 connections with 32 lift stations, 2,025 grinder pumps and 1,075, 1000 gallon, septic tanks.
N/A
M
CS
10-FEB-2023
14-FEB-2023
21-FEB-2023
27-MAR-2023
01-MAY-2023
30-APR-2028
N/A
No discharge allowed from this system
Collection system; 750,000 gpd effluent to Munford STP
.75
29-AUG-2024 08:40AM

Other DWR permits at this site

Permit Documents

View
Notice of ViolationSOP-98007_Late_Application_NOV30-SEP-2013
ApplicationRCVD VIA EMAIL 07-OCT-13: SOP app by Brian Koral.07-OCT-2013
LetterNotice of complete pmt app07-NOV-2013
Draft PermitDraft permit; PN 1/21/1423-JAN-2014
EmailRCVD VIA EMAIL 29-JAN-14: comments on draft from David Smith.29-JAN-2014
Old PermitFinal permit: Issue 4/1/1403-APR-2014
ReportCEI Report24-JUN-2014
Letter2015 Operator Form25-AUG-2015
Form2016 Certified Operator Form - Rec'd Via Email10-AUG-2016
Environmental Review16.0711 Information02-SEP-2016
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

no data found

Inspections

21-SEP-2021Compliance Evaluations (non-NPDES)In Compliance
22-MAR-2018Compliance Evaluations (non-NPDES)In Compliance
17-JUN-2014Compliance Evaluations (non-NPDES)In Compliance

Wastewater Engineering Plans Review

24.0505Review CompletePERTNH6/12/20247/16/2024Main St. and Kearns Lift Station Renovations
24.0226ApprovedCDTNH7/9/20247/16/2024Main St. and Kearns Lift Station Renovations
22.0573ApprovedCDMJB4/3/20244/10/2024Shepherd's Ridge Subdivision
19.0806ApprovedCDAWJ5/20/20205/26/2020Sterling Ridge Phase 7
19.0731ApprovedCDMNU12/17/201912/18/2019Oak Creek Subdivision Phase 5
19.0045Approved-MNU2/14/20192/14/2019Oak Creek S/D Phase 4
18.0944Approved-MNU12/12/20181/3/2019Sewer Plans for Cedar Ridge
18.0430Approved-MNU6/22/20187/17/2018Trinity Place
16.0711ApprovedLPCSA. Bahour5/1/20175/1/2017Deer Ridge, Phase 2
15.0528ApprovedLINEMNU9/14/201510/12/2015Oak Creek Subdivision-Phase 2