40474Martin Marietta Materials, Inc. dba Riverbend Quarry605 Cherokee Explosive Road RutledgeGraingerKnoxvilleView Map

Permit Information

TN0072516
Mining
Transferred to DMGR
BWI ETN LLC dba Blue Water Industries
Riverbend Quarry
Limestone quarry and processing facility
I
R
PW, SW
26-OCT-2020
09-NOV-2020
30-NOV-2020
23-MAR-2021
01-JUN-2021
31-MAY-2026
Holston River near mile 51 (just below Cherokee Dam)
treated mine wastewater and storm water
Settling/Treatment Ponds and BMPs
1422
22-JUL-2024 03:57PM

Other DWR permits at this site

No other permits found.

Permit Documents

View
Old Permit2000 New Permit Package12-MAY-2000
Inspection ReportBWI Riverbend Inspection Report13-AUG-2019
LetterDesignation of authorized signatories for BWI24-APR-2018
Draft PermitDraft 201515-DEC-2015
Draft PermitDraft NPDES Permit15-DEC-2020
PermitFinal NPDES Permit17-MAR-2016
PermitFinal NPDES Permit 23-MAR-2021
Inspection ReportInsp Report23-MAY-2019
Inspection ReportInsp. Report15-MAR-2016
ApplicationNPDES Application26-OCT-2020
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

08-DEC-2020Compliance Eval (non-sampling) (CEI)In Compliance
13-AUG-2019Compliance Eval (non-sampling) (CEI)In Compliance
23-MAY-2019Compliance Eval (non-sampling) (CEI)In Compliance
15-MAR-2016Compliance Eval (non-sampling) (CEI)In Compliance
18-MAR-2014Compliance Eval (non-sampling) (CEI)In Compliance
13-NOV-2013Compliance Eval (non-sampling) (CEI)In Compliance
14-JUN-2013Compliance Eval (non-sampling) (CEI)In Compliance
20-FEB-2013Compliance Eval (non-sampling) (CEI)In Compliance
23-OCT-2012Compliance Eval (non-sampling) (CEI)In Compliance
20-JUL-2012Compliance Eval (non-sampling) (CEI)In Compliance

Wastewater Engineering Plans Review