Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO NameGIS
168636Orr Development Phase 11335 E Wood StParisHenryJacksonView Map

Permit Information

TNR122650
CGP
Inactive
Jamie Orr
Bank Construction
N/A
16-JUN-2022
13-JUL-2022
13-JUL-2022
30-SEP-2026
10-JUL-2024
Bailey Fork Creek from Holly Fork Creek to headwaters (TN06040005024_0100)
10-JUL-2024 08:08AM

Other DWR permits at this site

Permit Documents

View
Notice of TerminationNOT acknowledgement email10-JUL-2024
Notice of TerminationNOT received24-JUN-2024
Notice of Coverage (NOC)CGP NOC13-JUL-2022
Notice of Intent (NOI)Orr NOI16-JUN-2022
SWPPPSWPPP drawings16-JUN-2022
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

no data found

CGP - Specific Information

Area Disturbed (acres)
.75
Start Date
7/31/2022
Estimated End Date
7/31/2023
Streams
No
Wetlands
No
Exceptional TN Waters (ETW)
No
ETW Comment
N/A
Threatened and Endangered Species 1 mile radius
No
Threatened and Endangered Species 5 miles downstream
No
Unavailable Conditions Waters
No
Unavailable Conditions Waters Comment
N/A
EPSC Plan Findings
-

Contractors

Contractor 1
Dean Howd
Start Date
5/31/2022
Contractor 2
-
Start Date
-
Contractor 3
-
Start Date
-
Contractor 4
-
Start Date
-
Contractor 5
-
Start Date
-
Contractor 6
-
Start Date
-