110683Memphis Regional Megasite101 Fredonia LoopStantonHaywoodJackson

Permit Information

TN0082368
Const-Individual
New
Ford Motor Company
Blue Oval City
site preparation and construction of manufacturing and warehousing units at the megasite from total area of disturbance estimated at 1,817 acres; the division concludes that proposed discharges will result in less than de minimis degradation of receiving streams
I
R
SW
18-MAR-2022
21-MAR-2022
18-JAN-2022
21-MAR-2022
21-MAR-2022
28-FEB-2027
unnamed tributaries to Big Muddy Creek and unnamed tributaries to Little Muddy Creek and wetlands on the site
stormwater runoff associated with construction activities from Outfalls 1, 2, 3A, 4A, 5A, 6, 7, 8, 9, 10A, 11, 12, 13, 14, 15A, 16, 17A, 18, 19 and 20
Best Management Practices (BMPs) and Erosion Prevention and Sediment Controls (EPSCs) such as grassed diversion ditches and channel outlets, rock check dams, filter socks, surface roughing, silt fences, sediment basins, rip-rap outlet protection, buffers
1629
07-SEP-2023 01:45PM

Other DWR permits at this site

  • 1 - 23 of 23
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
NRS24.151Becknell Services, LLCFredonia Road Improvement ProjectARAPCompleteN/AJackson---
TNR122929Becknell Services, LLCFredonia Road Improvements ProjectCGPActiveN/AJackson-16-AUG-2024-
TNR122890Ford Construction CompanyWaste Site for DB2301, SR-222, Haywood County, TNCGPActiveN/AJackson-30-APR-2024-
TNR122876Ford Construction CompanySR-222 North Reconstruction and WideningCGPActiveN/AJackson-20-MAR-2024-
NRS21.238Ford Motor CompanyBlue Oval CityARAPActiveMajorJackson22-MAR-202222-MAR-202221-MAR-2027
NRS08.260Haywood County-ARAPWithdrawnN/AJackson---
NRS22.127Memphis Regional Megasite AuthorityMemphis Regional Megasite, Site Water Piping and Sanitary Sewer Force MainARAPInactiveMinorJackson29-SEP-202229-SEP-202228-SEP-2027
TNR121565State of Tennessee - Department of General Services (DGS)Memphis Regional Megasite Linear Force MainCGPWithdrawnN/AJackson---
TN0081558State of Tennessee - Department of General Services (DGS)Memphis Regional Megasite Pump Station and LagoonsConst-IndividualInactiveN/AJackson---
TNR121567State of Tennessee - Department of General Services (DGS)Memphis Regional Megasite Pump Station and LagoonsCGPWithdrawnN/AJackson---
NRS13.248State of Tennessee - Department of General Services (DGS)Memphis Regional Megasite - Utility Crossing – Multiple Streams and WetlandsARAPWithdrawnN/AJackson---
NRS18.287State of Tennessee - Department of General Services (DGS)Memphis Regional Megasite Force Main 3ARAPInactiveN/AJackson---
NR1302.075State of Tennessee - Department of General Services (DGS)Wastewater force main and on-site water distribution system - Memphis Regional MegasiteARAPWithdrawnN/AJackson---
TNR121562State of Tennessee - Department of General Services (DGS)Memphis Regional Megasite Water MainCGPWithdrawnN/AJackson---
TNR121564State of Tennessee - Department of General Services (DGS)Memphis Regional Megasite South Water TowerCGPInactiveN/AJackson-08-JAN-2014-
TNR121984State of Tennessee - Department of General Services (DGS)Memphis Regional Megasite - LagoonCGPInactiveN/AJackson-27-OCT-201730-SEP-2026
TNR154400State of Tennessee - Department of General Services (DGS)Force Main 1, 2 and 3CGPInactiveN/AJackson-26-JUL-201730-SEP-2026
TNR121566State of Tennessee - Department of General Services (DGS)Memphis Regional Megasite Water Treatment PlantCGPInactiveN/AJackson-08-JAN-201430-SEP-2026
TNR121563State of Tennessee - Department of General Services (DGS)Memphis Regional Megasite North Water TowerCGPInactiveN/AJackson-08-JAN-201430-SEP-2026
NRS17.054State of Tennessee - Department of General Services (DGS)Memphis Megasite - Installation of 18 inch HDPE Force Main to the Mississippi RiverARAPInactiveMinorJackson01-MAY-201801-MAY-201830-APR-2023
NRS23.237Tennessee Department of Transportation (TDOT)24S222-S1-003; PIN 132132.04 (Project Blue Oval)ARAPActiveMajorJackson23-APR-202423-APR-202422-APR-2029
NRS23.159Tennessee Department of Transportation (TDOT)PIN 132709.00, PE #R4S222-S1-002ARAPActiveMinorJackson16-OCT-202316-OCT-202315-OCT-2028
TNR192282Tennessee Department of Transportation (TDOT)PE No.: 24S222-S1-003; PIN: 132132.04; I-40 at S.R. 222 interchangeCGPActiveN/AJackson-17-MAY-202430-SEP-2026
  • 1 - 23 of 23

Permit Documents

View
LetterTN0082368 Email chain with response from Ford per 11/1/24 letter with associated attachments06-DEC-2024
LetterTN0082368 Signatory Authority Letter regarding site inspections being delegated to Blake Newbill.22-NOV-2024
LetterTN082368 Ford response to TDEC's 11/1/24 letter22-NOV-2024
LetterTN0082368 Follow-up letter to July 19 2024 CEI01-NOV-2024
SWPPPTN0082368 SWPPP Certification Page adding E&L Construction (Nate Spurlin) as contractor09-SEP-2024
EmailTN0082368 Email explanation regarding revised EPSC plans July 2024 showing new access road along south side of BOSK09-AUG-2024
LetterTN0082368 - Response from Ford regarding May 2024 CEI09-AUG-2024
SWPPPTN0082368 SWPPP certification page adding Clark & Sons Construction as contractor07-AUG-2024
Engineering Drawings-PlansTN0082368 Revised EPSC plans July 2024 showing new access road along south side of BOSK23-JUL-2024
Inspection ReportTN0082368 CEI19-JUL-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

29-MAY-2024Compliance Eval (non-sampling) (CEI)Out of Compliance
09-JAN-2024Compliance AssistanceOut of Compliance
01-AUG-2023Follow-upOut of Compliance
13-JUN-2023Follow-upOut of Compliance
17-APR-2023Compliance Eval (non-sampling) (CEI)Out of Compliance
24-JUN-2022Compliance Eval (non-sampling) (CEI)In Compliance