Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5185Harriman STP504 Bullard Ford RoadHarrimanRoaneKnoxville

Permit Information

TN0025437
Individual
Reissuance
City of Harriman
Harriman STP
Screening, grit removal, biological treatment via oxidation ditches and center feed-peripheral withdrawal clarifiers, and chlorine disinfection. Waste activated sludge is aerobically digested, dewatered with a belt filter press prior to land application.
M
M
MW
30-NOV-2020
03-DEC-2020
15-DEC-2020
20-JAN-2021
01-FEB-2021
31-JAN-2026
Outfall 001 -Tennessee River at mile 567 or Outfall 002 - Emory River (10.5)
Treated municipal wastewater from Outfalls 001 or 002
Screening, grit removal, biological treatment via oxidation ditches and center feed-peripheral withdrawal clarifiers, and chlorine disinfection. Waste activated sludge is aerobically digested, dewatered with a belt filter press prior to land application.
4952
1.5
08-JUL-2024 03:41PM

Other DWR permits at this site

Permit Documents

View
LetterRcvd: nofn of rcvd appl at K-EFO by WLS.01-JUN-2011
LetterRcvd: comments on Draft by Bill Young.24-AUG-2011
ReportHarriman, TN, Emory River Flow Evaluation and Request for a Second Discharge Location19-SEP-2011
LetterCEI by AWB.20-JUL-2012
LetterCEI Report05-MAR-2014
EmailRCVD 22-MAY-14: email re: mailing address by Candace Vannasdale. 22-MAY-2014
LetterFOLLOW-UP LETTER11-AUG-2014
Form2015 WW Operator Form14-SEP-2015
ApplicationRCVD VIA EMAIL 24-NOV-15: NPDES app by William Young.24-NOV-2015
LetterOctober 16 2015 Meeting summary23-DEC-2015
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

OverflowsEFO CommunicationRobert Ramsey email 4/16/194/17/2019Closed

Inspections

11-APR-2024Compliance AssistanceIn Compliance
24-JUN-2020Compliance AssistanceIn Compliance
19-MAR-2020Compliance AssistanceIn Compliance
28-SEP-2021Compliance Biomonitoring (CBI)In Compliance
07-APR-2023Compliance Eval (non-sampling) (CEI)In Compliance
14-MAY-2019Compliance Eval (non-sampling) (CEI)In Compliance
20-SEP-2017Compliance Eval (non-sampling) (CEI)In Compliance
17-FEB-2016Compliance Eval (non-sampling) (CEI)In Compliance
11-FEB-2014Compliance Eval (non-sampling) (CEI)In Compliance
16-JUL-2012Compliance Eval (non-sampling) (CEI)In Compliance

Wastewater Engineering Plans Review

24.0181ApprovedCDTNH3/8/20244/9/2024ARPA Sanitary Sewer Rehabilitation
23.0607ApprovedCDMJB11/9/202311/27/2023Pine Ridge Road Sewer Extension
23.0600ApprovedCDMJB12/4/202312/12/2023Emory Creek Subdivision Phase 1
23.0304ApprovedCDA. Bahour7/13/20237/13/2023Harriman Utility Board Standard Specifications
21.0584Review CompleteCDTNH7/27/2021-Clarifier No. 2 Rehabilitation and Repainting
18.0239ApprovedCDA. Bahour5/17/20185/17/2018Highland View, Phase 2
14.0450ApprovedLINEMNU7/14/20148/20/2014State Route 29
12.0488Review CompletePERJMS7/26/20128/16/2012CDBG-2012 - Harriman Sewer System Improvements Project
00.0259ApprovedSTDSPECMNU3/2/20004/4/2000STD SPECS
18.0687Review Complete-Jim McAdoo8/1/20188/3/2018Wastewater Treatment Plant Clarifier No 1