Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
4973Tennessee Valley Authority (TVA) - John Sevier Fossil Plant (JSF)299 TVA Pond RoadRogersvilleHawkinsJohnson City

Permit Information

NRS13.249
ARAP
Construction of Intake and Outfall Structures
Inactive
Tennessee Valley Authority (TVA)
John Sevier Fossil Plant - ground water discharge Intake/Outfall Stucture at Cherokoee Reservoir
construction of a ground water outfall at John Sevier Detention Reservoir
N/A
23-DEC-2013
18-FEB-2014
18-FEB-2014
14-MAR-2014
14-MAR-2014
30-JUN-2015
04-AUG-2015
Cherokoee Reservoir
01-JUN-2023 01:51PM

Other DWR permits at this site

  • 1 - 31 of 31
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
SOP-11025John Sevier Combine Cycle Plant (JCC)Turbine compressor wash water pump and haulSOPInactiveN/AJohnson City31-JAN-201201-FEB-201231-JAN-2017
TNG670370John Sevier Fossil (JSF) Plant-HydrostaticInactiveN/AJohnson City12-APR-201112-DEC-201131-DEC-2012
TNG670372John Sevier Mainline Extension-HydrostaticInactiveN/AJohnson City28-MAR-201128-MAR-201130-DEC-2011
TNR169995Tennessee Valley Authority (TVA)TVA-John Sevier Fossil PlantCGPInactiveN/AJohnson City---
TN0081141Tennessee Valley Authority (TVA)John Sevier Combined Cycle Combustion Turbines (JCC)IndividualInactiveN/AJohnson City---
NRS15.054Tennessee Valley Authority (TVA)John Sevier Fossil Plant - - Construct New Industrial Wastewater Outfall to Discharge Dry Fly Ash Stack Toe Drain, Leachate and Stormwater at Cherokee Reservoir and Holston RiverARAPWithdrawnN/AJohnson City---
TNR191468Tennessee Valley Authority (TVA)John Sevier Fossil Plant DemolitionCGPInactiveN/AJohnson City-11-DEC-2015-
NRS15.275Tennessee Valley Authority (TVA)John Sevier Fossil Plant - Ash Disposal Area J - Stormwater Outfall Replacement at Holston River and Cherokee ReservoirARAPWithdrawnN/AJohnson City06-OCT-201506-OCT-2015-
NR1506.013Tennessee Valley Authority (TVA)TVA-John Sevier Fossil PlantARAPInactiveN/AJohnson City23-APR-201523-APR-2015-
TNR191333Tennessee Valley Authority (TVA)JSF - Drystack ClosureCGPInactiveN/AJohnson City-05-NOV-2014-
TNR191261Tennessee Valley Authority (TVA)John Sevier Fossil - Sanders Property CleanupCGPInactiveN/AJohnson City-21-AUG-2012-
TNR191262Tennessee Valley Authority (TVA)JSF - Bottom Ash Pond Discharge Re-Route ProjectCGPInactiveN/AJohnson City-21-AUG-2012-
TNR191029Tennessee Valley Authority (TVA)John Sevier Fossil PlantCGPInactiveN/AJohnson City-08-AUG-2011-
TNR191021Tennessee Valley Authority (TVA)John Sevier Fossil Combine FacilityCGPInactiveN/AJohnson City-11-MAR-2010-
TNR191009Tennessee Valley Authority (TVA)John Sevier Fossil Combine Facility Access RoadCGPInactiveN/AJohnson City-18-DEC-2009-
TNR190887Tennessee Valley Authority (TVA)Located on TVA Reservation on Dru Hanes Road near Dodson CreekCGPInactiveN/AJohnson City-01-APR-2009-
TNR190657Tennessee Valley Authority (TVA)John Sevier Fossil Plant - Borrow AreaCGPInactiveN/AJohnson City-20-SEP-2006-
TNR053187Tennessee Valley Authority (TVA)John Sevier Fossil and Combined Cycle PlantsTMSPActiveN/AJohnson City19-JUL-202020-JUL-202030-JUN-2025
TN0005436Tennessee Valley Authority (TVA)John Sevier Combined Cycle Plant (JCC)IndividualReissuanceMajorJohnson City01-APR-202001-JUN-202031-DEC-2024
NRS15.306Tennessee Valley Authority (TVA)TVA - J-Pond Shoreline Scour Protection at Holston River and Cherokee ReservoirARAPInactiveMinorJohnson City05-FEB-201605-FEB-201604-FEB-2021
SOP-12003Tennessee Valley Authority (TVA)Pump and haul associated with fossil plant construction; SOP-10001 is pump and haul associated with combined cycle plant construction.SOPInactiveN/AJohnson City30-APR-201201-MAY-201230-APR-2017
NRS13.080Tennessee Valley Authority (TVA)John Sevier Fossil Plant - Dry Fly Ash Stack - Stormwater Outfall Construction at Cherokee Reservoir and Holston RiverARAPInactiveN/AJohnson City31-MAY-201331-MAY-201330-JUN-2015
NRS12.145Tennessee Valley Authority (TVA)TVA John Sevier Fossil Plant Discharge RelocationARAPInactiveN/AJohnson City26-JUL-201226-JUL-201230-JUN-2015
NRS10.123Tennessee Valley Authority (TVA)-ARAPInactiveN/AJohnson City18-MAY-201018-MAY-201017-MAY-2015
SOP-10001Tennessee Valley Authority (TVA)TVA-John Sevier Combined Cycle PlantSOPInactiveN/AJohnson City26-FEB-201011-MAR-201027-FEB-2015
NRS08.228Tennessee Valley Authority (TVA)TVA-John Sevier Fossil PlantARAPInactiveN/AJohnson City--21-SEP-2011
NRS06.225Tennessee Valley Authority (TVA)-ARAPInactiveN/AJohnson City11-SEP-200611-SEP-200611-SEP-2009
NRS06.407Tennessee Valley Authority (TVA)-ARAPInactiveN/AJohnson City08-DEC-200608-DEC-200631-OCT-2007
NRS05.342Tennessee Valley Authority (TVA)-ARAPInactiveN/AJohnson City02-NOV-200502-NOV-200502-NOV-2006
TNR190043Tennessee Valley Authority (TVA)TVA-John Sevier Fossil Plant Bank Stabilization ProjectCGPInactiveN/AJohnson City-06-APR-200131-MAY-2005
NRS01.089Tennessee Valley Authority (TVA)-ARAPInactiveN/AJohnson City--18-MAR-2003
  • 1 - 31 of 31

Permit Documents

View
ApplicationARAP Permit Application23-DEC-2013
LetterARAP Permit Application Received - Assigned to Permit Writer06-JAN-2014
PermitARAP Permit Issued18-MAR-2014
Emailmore detail for application18-FEB-2014
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

no data found