Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5621White House STP725 Industrial DriveWhite HouseRobertsonNashville

Permit Information

TN0059404
Individual
Reissuance
City of White House
White House STP
Treatment of municipal sewage. WWTP expansion from 1.4 to 2 MGD via 5-stage Bardenpho bioreactor with effluent filtration to maintain existing pollutant loads. Incidental degradation is justified by area-wide development.
M
M
MW
07-MAR-2024
05-FEB-2019
19-MAR-2024
26-MAR-2024
29-APR-2024
01-JUN-2024
31-MAY-2029
Frey Branch at mile 2.2
treated municipal wastewater from Outfall 001 and disposal by land application on adjacent POTW property
oxidation ditch activated sludge with UV disinfection and final cascade aeration; some treated effluent disposal via land irrigation via storage pond. 2/18/2009 - Not currently using spray irrigation - JEH
4952
2
13-AUG-2024 07:30AM

Other DWR permits at this site

  • 1 - 4 of 4
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR245312City of White HouseWhite House WWTP ImprovementsCGPActiveN/ANashville-01-SEP-202130-SEP-2026
NR1904.275City of White HouseWhite House WWTP Improvements (Outfall Structure)ARAPInactiveN/ANashville-02-DEC-201906-APR-2020
NR2104.255City of White House White House WWTP Improvements (Maintenance Activities)ARAPActiveN/ANashville-31-AUG-202107-APR-2025
TNB059404White House STP-BiosolidsInactiveN/ANashville---
  • 1 - 4 of 4

Permit Documents

View
LetterWPN24.0707 Approval Letter 2024100101-OCT-2024
EmailPT IWS26-SEP-2024
ReportTIE/TRE Progress Report23-SEP-2024
Letter24.0617 Plans Approval LTR 2024081515-AUG-2024
EmailJuly 2024 eMOR- operator concerned inf and eff numbers are switched, 08-AUG-2024
Letter24.0184 Approval letter 2024080606-AUG-2024
EmailPT IWS Reminder29-JUL-2024
Letter24.0436 Approval letter 2024072525-JUL-2024
Monitoring ReportJune eMOR- 100% on the new 2.0 MGD plant. The west basin (basin 1) had some serious electrical failures during testing. The east basin (basin 2) has been operating since May 6th.15-JUL-2024
Letter24.0498 Plans Approval LTR 2024070202-JUL-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

no data found

Inspections

18-FEB-2009Compliance Eval (non-sampling) (CEI)In Compliance
15-JUL-2008Compliance Sampling (CSI)In Compliance
23-SEP-2013Compliance Eval (non-sampling) (CEI)Minor Deficiency Noted
08-NOV-2011Compliance Eval (non-sampling) (CEI)Minor Deficiency Noted
28-APR-2010Enforcement Case SupportMinor Deficiency Noted
29-NOV-2006Performance Audit (PAI)NOV
07-MAR-2010Compliance Biomonitoring (CBI)Order Requested
04-APR-2023Compliance Sampling (CSI)Out of Compliance
12-MAY-2021Compliance Eval (non-sampling) (CEI)Out of Compliance
10-MAY-2019Compliance Biomonitoring (CBI)Out of Compliance

Wastewater Engineering Plans Review

12.0288ApprovedLINEPhil Simmo6/15/20126/20/2012Emerald Point Phase Seven
12.0114COApprovedCOPhil Simmo10/25/201312/5/2013SRF - Hobbs Area and Dawn Court
13.0774Approved-A. Bahour12/26/20131/2/2014Standard Sewer Specifications
13.0660ApprovedLPCSA. Bahour11/1/20131/6/2014Utility Extension for Magnolia Place
14.0002ApprovedPSFMPhil Simmo1/2/20141/7/2014SRF - Sage Road Sanitary Sewer Improvements
14.0437ApprovedLINEMNU7/9/20148/14/2014Sage Road Apartment
14.0526ApprovedLINEMNU8/6/20148/28/2014Durham Farms, Phase 1, Section 1
14.0525ApprovedLINEMNU8/6/20148/28/2014Durham Farms, Phase 1, Section 5
14.0524ApprovedLINEMNU8/6/20148/28/2014Durham Farms, Phase 1, Section 4
14.0674ApprovedERPhil Simmo8/29/20149/18/2014SRF - Northern Force Main and Calista Vacuum Pump Station Improvements & Union Road Force Main Extension