174953PIN 131306.00, Project # 57201-1159-44Madison County, I-40, Interchange at SR-138 Exit 68JacksonMadisonJacksonView Map

Permit Information

NRS24.063
ARAP
Individual Permit
Complete
Tennessee Department of Transportation (TDOT)
PIN 131306.00 - Ramp Improvement
The Tennessee Department of Transportation proposes 309 feet of impacts to Panther Creek for a culvert extension and rip rap accommodating ramp improvements at the I-40 and State Route 138 Interchange in Madison County. Compensatory mitigation for loss of 94.1 functional feet of stream will be through purchase of 141.15 credits the from Rossville Farm Mitigation Bank.
M
09-APR-2024
16-JUL-2024
16-JUL-2024
Panther Creek
16-JUL-2024 01:14PM

Other DWR permits at this site

No other permits found.

Permit Documents

View
Engineering Drawings-PlansUpdated engineering plans01-AUG-2024
Engineering Drawings-PlansUpdated permit sketches01-AUG-2024
AddendumUpdated Feature Impact Tables01-AUG-2024
LetterUpdate to file request01-AUG-2024
LetterApplicant Letter of Responsibility 16-JUL-2024
Public Notice DocumentPublic Notice Document 16-JUL-2024
EmailPublic Notice Email16-JUL-2024
AddendumUpdated Mitigation Ledger16-JUL-2024
Draft PermitDraft Permit16-JUL-2024
EmailAcknowledgment of Application Email11-APR-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections