Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5005Rogersville STP620 Flora LaneRogersvilleHawkinsJohnson City

Permit Information

TN0020672
Individual
Reissuance
Town of Rogersville
Rogersville STP
Treatment of municipal sewage via the activated sludge process and chlorine disinfecting.
M
M
MW
03-JUN-2024
03-JUN-2024
03-JUN-2024
26-NOV-2024
29-NOV-2019
01-JAN-2020
31-DEC-2024
Cherokee Reservoir at Holston River mile 99.7
treated municipal wastewater from Outfall 001
Influent screening, activated sludge plant with chlorination; Storm flow – receives primary treatment, disinfection and blending with treated effluent prior to discharge. Sludge is aerobically digested and dewatered via a belt press for land application
4952
1.3
26-NOV-2024 02:11PM

Other DWR permits at this site

  • 1 - 1 of 1
  • 1 - 1 of 1

Permit Documents

View
Monitoring ReportRogersville WWTP November 2024 MOR 06-DEC-2024
Draft PermitDraft Permit26-NOV-2024
SpreadsheetPT PTL Spreadsheet25-NOV-2024
LetterPT PTL Town Ltr25-NOV-2024
Monitoring ReportRogersville WWTP October 2024 MOR 08-NOV-2024
Monitoring ReportRogersville WWTP September 2024 MOR 04-OCT-2024
Monitoring ReportRogersville WWTP August 2024 MOR 06-SEP-2024
Monitoring ReportRogersville WWTP July 2024 MOR 08-AUG-2024
Notice of ViolationPT SAR NOV09-JUL-2024
Corrective Action PlanRogersville STP CAP response to PCI inspection report (inspection conducted on May 20, 2024)08-JUL-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

20-MAY-2024Pretreatment Compliance (oversight)In Compliance
01-JUN-2023Pretreatment TAV and File ReviewIn Compliance
17-MAY-2023Sanitary Sewer Overflow Non-SamplingIn Compliance
17-MAY-2023Compliance Eval (non-sampling) (CEI)In Compliance
24-MAY-2022Pretreatment Compliance (oversight)In Compliance
28-FEB-2022Follow-upIn Compliance
08-SEP-2021Pretreatment AuditPending
03-JUN-2021Compliance AssistanceOut of Compliance
06-APR-2021Sanitary Sewer Overflow Non-SamplingOut of Compliance
06-APR-2021Compliance Eval (non-sampling) (CEI)Out of Compliance

Wastewater Engineering Plans Review

23.0248ApprovedCDA. Bahour5/16/20236/9/2023Ross Circle Sewer LIne
20.0450ApprovedCDMJB9/15/20209/15/2020South Armstrong Road Utility Relocation
20.0550ApprovedCDAWJ9/2/20209/14/2020The Town of Rogersville Standard Specifications
20.0293ApprovedCDAWJ8/11/20208/31/2020Rogersville Wastewater Treatment Plant Influent Screens Equipment Project
13.0446ApprovedCAP/ERPhil Simmo7/15/20137/31/2013Rogersville Wastewater Treatment Plant
93.805ApprovedSTDSPECSPW11/4/199312/10/1993STD SPECS
19.0103InactivePP-ERAWJ7/18/2019-Improvements to the Rogersville WWTP NPDES Permit # TN0020672
17.0012Review CompleteCMOMWDM1/4/2017-CMOM Review
14.0180Review CompleteSORPWDM3/27/2014-Rogersville Water Commission SOP