Site IDSiteLocationCityCountyEFO Name
5109Turkey Creek WWTP (Morristown STP)1722 Tyler RoadMorristownHamblenKnoxville

Permit Information

TN0023507
Individual
Reissuance
Morristown Utilities Commission
Turkey Creek Wastewater Treatment Plant
Treatment of municipal sewage by aerobic digestion, chlorination, and dechlorination
M
M
MW
26-APR-2024
16-APR-2019
22-MAY-2024
17-DEC-2024
08-OCT-2019
01-NOV-2019
31-OCT-2024
Holston River Mile 75
treated municipal wastewater from Outfall 001
Treatment includes screening, grinding, grit removal, primary settling in clarifiers, aerobic digestion using aeration basins, secondary clarifiers, chlorination, and dechlorination. Sludge is treated by aerobic digestion and disposed at landfill
4952
7.5
16-DEC-2024 02:00PM

Other DWR permits at this site

Permit Documents

View
Form ceiform1421-APR-2014
Report April 2016 SAR PT 02-MAY-2016
Email15-0568 E-mail String21-APR-2016
Letter16-0314 Approval letter17-MAY-2016
Letter16-0314 Cover letter25-APR-2016
Environmental Review16-0335 Information27-APR-2016
Letter16-0515 Approval letter02-SEP-2016
Email16-0515 E-mail02-SEP-2016
Environmental Review16-0515 Information01-JUL-2016
Letter16-0553 Letter03-AUG-2016
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

Director's Order8/1/2016Watch List28

Inspections

23-JUL-2024Compliance Eval (non-sampling) (CEI)In Compliance
10-JUL-2024Compliance Eval (non-sampling) (CEI)In Compliance
12-FEB-2024Pretreatment Compliance (oversight)In Compliance
03-JAN-2023Pretreatment TAV and File ReviewIn Compliance
11-AUG-2022Compliance Eval (non-sampling) (CEI)In Compliance
28-FEB-2022Pretreatment Compliance (oversight)In Compliance
01-APR-2021Pretreatment AuditOut of Compliance
13-JAN-2020Pretreatment TAV and File ReviewIn Compliance
26-JUN-2019Compliance Eval (non-sampling) (CEI)In Compliance
05-FEB-2018Pretreatment TAV and File ReviewIn Compliance

Wastewater Engineering Plans Review

24.0830PendingCDRGO11/9/202411/28/2024Spring Creek Sewer Extension
24.0804PendingCDMJT10/28/202411/26/2024Airplane Hangars
24.0653PendingCDMJT8/21/202411/18/2024Valley Ridge Subdivision
24.0306PendingCDMJT4/22/20247/22/2024Village Greene
23.0748PendingCDJKM11/30/20232/8/2024Bell Property
23.0214PendingCDMJB4/20/20235/15/2023Windswept Development - Phase IV - Unit 2
23.0171PendingCDMJB3/23/20234/11/2023Southwood Subdivision
23.0056PendingCDMJB1/31/20234/11/2023Millstone Subdivision - Phase I
22.0705PendingCDMJB11/8/202212/12/2022Turkey Creek Wastewater Treatment Plant Aeration and Raw Sewage Flume Improvements
22.0423ApprovedCDA. Bahour10/24/202210/24/2022Bellwood Farms