Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5832Monteagle STP, Plant #3Highway 64 WestMonteagleGrundyChattanooga

Permit Information

TN0080985
Individual
Reissuance
Town of Monteagle
Monteagle Sewer Treatment Plant #3
treatment of domestic wastewater with a 0.5 MGD sequencing batch reactor with chlorination
I
M
MW
23-MAR-2022
13-APR-2022
30-AUG-2022
30-SEP-2022
01-OCT-2022
30-SEP-2027
unnamed tributary to Gilliam Creek (001) and an unnamed tributary mile 1.0 to Trussell Creek (002)
treated municipal wastewater
Sequencing batch reactor with post equilization, UV disinfecting, step aeration
4952
.5
08-JUL-2024 03:41PM

Other DWR permits at this site

  • 1 - 7 of 7
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
TNR111878City of MonteagleMonteagle Wastewater Treatment Plant #3CGPInactiveN/AChattanooga-24-MAR-2010-
TNB064815Monteagle STP-BiosolidsInactiveN/AChattanooga---
TN0064815Monteagle STP, Plant #2-IndividualInactiveMinorChattanooga31-MAY-200801-JUL-200831-MAY-2012
TNB080985Monteagle STP, Plant #3-BiosolidsActiveN/AChattanooga14-JUL-201414-JUL-201430-APR-2019
NR1001.001Town of Monteagle-ARAPInactiveN/AChattanooga-12-JAN-201030-JUN-2010
NR1001.002Town of Monteagle-ARAPInactiveN/AChattanooga-12-JAN-201030-JUN-2010
NR1001.003Town of Monteagle-ARAPInactiveN/AChattanooga-11-JAN-201030-JUN-2010
  • 1 - 7 of 7

Permit Documents

View
ReportQuarterly Report (Q4 2024)15-OCT-2024
Inspection ReportCEI13-SEP-2024
ReportCorrective Action Plan29-AUG-2024
EmailInitial TNPOP assessment and sampling recommendations22-AUG-2024
LetterResponse to NOV dated 30-MAY-2425-JUN-2024
Notice of ViolationNOV for effluent violations on EPA's QNCR from November 2023 to April 202430-MAY-2024
LetterWPN24.0080 Approval Letter 2024031418-MAR-2024
MemoWPN24.0017 ARP Memo 2024011212-JAN-2024
FormPT IWS18-AUG-2023
LetterResponse to NOV dated 16-MAY-2312-JUN-2023
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

I/I:O & M:Overflows:WWTP OverloadAgreed OrderThe moratorium is no longer active. The order was never finalized and the facility has only reported 1 overflow in the past 2 years. Verified with CH-EFO. (EJM 2-15-2019)1/24/2006Closed58

Inspections

04-JUN-2024Sanitary Sewer SystemIn Compliance
22-JUL-2021Compliance Sampling (CSI)Out of Compliance
19-APR-2017Compliance Eval (non-sampling) (CEI)Out of Compliance
09-JAN-2013Compliance Eval (non-sampling) (CEI)Follow-up Inspection Required

Wastewater Engineering Plans Review

24.0766PendingCDMJB12/2/2024-Willow Breeze Townhomes
24.0080PendingCDTNH1/31/20243/18/20242023 Sanitary Sewer Rehabilitation Project
24.0017PendingPERTNH1/5/20241/12/20242023 Sanitary Sewer Rehabilitation Project
15.0398Inactive-PJH6/25/2015-WWTP-Alternative Disinfection Fee
09.0778ApprovedPSFMA. Bahour10/21/200910/28/2009ARRA - Wastewater Treatment Plant and Phases 1 and 2 Collection System Replacement