Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5015Oliver Springs STP435 Joel RoadOliver SpringsRoaneKnoxville

Permit Information

TN0020885
Individual
Reissuance
Town of Oliver Springs
Oliver Springs STP
Oxidation ditch activated sludge plant with chlorination/dechlorination
I
M
MW
13-APR-2023
26-APR-2023
09-MAY-2023
12-JUN-2023
01-JUL-2023
30-JUN-2028
Poplar Creek at mile 15.4
treated municipal wastewater from Outfall 001
Equalization and Oxidation ditch activated sludge plant with biological nutrient removal, secondary clarification, chlorination/dechlorination and effluent filtration/aeration
4952
.74
08-JUL-2024 03:41PM

Other DWR permits at this site

Permit Documents

View
Monitoring ReportJune 2024 MOR16-JUL-2024
Monitoring Reportapr 24 MOR21-MAY-2024
LetterWPN24.0237 Approval Letter 2024042525-APR-2024
FormMOR-March-2418-APR-2024
ReportEngineer-Contract03-APR-2024
ReportSewer-Rehab-Plan03-APR-2024
LetterSelf-imposed moratorium-letter02-APR-2024
LetterLetter informing permit holder that manhole C8 has reached the 6 overflow in 12 month period and a self-imposed moratorium must now be enforced.02-APR-2024
MemoSite-visit-2428-MAR-2024
MemoWPN24.0169 ARP Memo 2024032727-MAR-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

I/IPermitSelf-Imposed Moratorium for 6 overflows at manhole C8 from June 23 to Feb 24. See notification letter.4/2/2024Watch List77

Inspections

31-JUL-2024Compliance Sampling (CSI)Pending
13-OCT-2022Compliance Eval (non-sampling) (CEI)Out of Compliance
24-SEP-2021Compliance Sampling (CSI)In Compliance
20-AUG-2018Compliance Sampling (CSI)Out of Compliance
13-JUN-2018Compliance AssistanceOut of Compliance
23-MAY-2018Compliance AssistanceOut of Compliance
06-APR-2018Compliance AssistanceOut of Compliance
16-MAR-2018Compliance AssistanceOut of Compliance
06-FEB-2018Compliance AssistanceOut of Compliance
04-JAN-2018Compliance AssistanceOut of Compliance

Wastewater Engineering Plans Review

24.0237ApprovedCDMJT4/2/20244/25/20242024 ARPA Sewer System Sewer Rehabilitation
24.0169Review CompletePERTNH3/5/20243/27/2024PER for Oliver Springs - Basin 3 (C) - I/I Rehab
21.0240ApprovedCDTNH4/22/20215/7/2021RD Sanitary Sewer System Rehab Contract III-B-Renovation of Joel Road Pump Station
19.0096ApprovedCDJAH3/8/20193/11/2019RD Sanitary Sewer System Rehab Contract III-A-Renovation of Pump 2 and 3
17.0722ApprovedotherRGO10/20/201711/9/2017RD Sanitary Sewer System Rehab Contract II
17.0039ApprovedIMPJAH1/20/20171/27/2017Norwood Area
17.0011Review CompleteADDSEF1/9/20171/11/2017SRF-Oliver Springs WWTP Improvements Phase III
16.0785Review CompleteIMPSEF9/20/201610/5/2016SRF-Contract 3 of 3 WWTP Improvements Phase III
16.0409Review CompleteotherSEF5/25/20166/8/2016SRF- Contract WWTP Sludge Dewatering System Phase I
16.0089Review CompleteCS CAP/ERSEF1/4/20162/17/2016Oliver Springs STP CS CAP-ER