Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
5168Springfield Water and Wastewater Department - Wastewater Treatment Plant530 Lawrence LaneSpringfieldRobertsonNashville

Permit Information

TN0024961
Individual
Reissuance
City of Springfield
Springfield STP
Treatment of municipal sewage; Reissue with expanded design capacity proposes to replace the 38 year-old, 3.44 MGD, extended aeration activated sludge process with a 7.0 MGD, 4-basin, sequencing batch reactor process, effluent equalization, disc filtration and ultraviolet light disinfecting to maintain existing loadings of oxygen-demanding pollutants and realize higher levels of nutrient removal. Incidental degradation that may still result in spite of the higher level of treatment will not result in pollution and is justified to support area-wide residential and industrial growth.
M
M
MW
21-JUN-2024
17-JUL-2024
29-OCT-2024
06-JUL-2020
01-AUG-2020
31-DEC-2024
Sulphur Fork Creek at mile 23.2 (current 3.44 MGD POTW); Confluence of Carr Creek at mile 0 and Sulphur Fork Creek at mile 23.0 (future 7.0 MGD POTW)
treated municipal wastewater from Outfall 001 (both the existing and new outfall replacing it)
Extended aeration activated sludge preceded by screening and grit removal and followed by ultraviolet disinfecting and oxygenation. Sludge is digested for either belt press dewatering or land application.
4952
3.4
30-OCT-2024 08:10AM

Other DWR permits at this site

  • 1 - 4 of 4
Permit NoPermittee NameProject NamePermit TypeStatusRatingEFO Name__Issuance___Effective___Expiration__
NR2304.044City of SpringfieldCity of Springfield WWTPARAPActiveN/ANashville-02-MAR-202307-APR-2025
TNB024961Springfield STP-BiosolidsActiveN/ANashville06-MAR-201806-MAR-201830-APR-2019
TNR056426Springfield Wastewater Treatment Plant-TMSPActiveN/ANashville19-JUL-202020-JUL-202030-JUN-2025
NRS14.299Springfield Water and Wastewater DepartmentBeans Cave Sewer Repair at Unnamed Tributary to Sulphur Fork CreekARAPInactiveN/ANashville--30-JUN-2015
  • 1 - 4 of 4

Permit Documents

View
SpreadsheetPT PTL Spreadsheet04-NOV-2024
LetterPT PTL Twn Ltr04-NOV-2024
Inspection Report2023-2024 PCI - In compliance01-NOV-2024
Inspection Report2023-2024 PCI - Inspection01-NOV-2024
Draft PermitTN0024961 2024 draft reissue with expanded design capacity30-OCT-2024
Letter24.0671 Plans Approval LTR 2024090303-SEP-2024
EmailCourtesy records keeping requirements21-AUG-2024
LetterWPN24.0448 Approval Letter 2024081619-AUG-2024
LetterWPN 22.0374 Extension Letter 07.29.202429-JUL-2024
LetterWPN 23.0137 Extension Letter 07.26.202426-JUL-2024
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Inspections

06-JUN-2005Compliance Biomonitoring (CBI)Minor Deficiency Noted
20-APR-2006Pretreatment TAV and File ReviewIn Compliance
14-FEB-2007Compliance Eval (non-sampling) (CEI)In Compliance
18-MAY-2007Pretreatment Compliance (oversight)In Compliance
26-JUN-2007Biosolids InspectionMinor Deficiency Noted
13-JUN-2008Pretreatment AuditNOV
04-JUN-2009Pretreatment Compliance (oversight)NOV
21-JUL-2009Performance Audit (PAI)Minor Deficiency Noted
15-JUL-2010Compliance Sampling (CSI)In Compliance
03-AUG-2010Pretreatment TAV and File ReviewIn Compliance

Wastewater Engineering Plans Review

97.0110ApprovedSTDSPECWDM2/4/19975/5/1998STD SPECS (2 REVISED SETS REC'D 4/13/98)
05.0570Approved-A. Bahour5/24/20056/27/2005TANGLEWOOD S/D
13.0678ApprovedREHABA. Bahour11/14/201312/13/2013Priority Basins Rehab Phase 1B - Basins 13 & 14
14.0086ApprovedREHABMNU2/10/20142/18/2014Priority Basins Rehabilitation Phase 1A-Basin 3BCC
14.0420ApprovedLINEMNU6/20/20148/4/2014Crestview Elementary School
14.0642ApprovedREHABMNU8/15/20149/18/2014Rehab. of approx. 26,000 liner feet of sewer line Phase 2A-Basins 3 & 4A
14.0812ApprovedSTDSPECA. Bahour11/4/201411/24/2014Standard Sewer Specifications
14.0782ApprovedREHABMNU10/16/201411/24/2014Constructed Basins Rehabilitation Phase 2B - Basins 4B & 5
14.0731ApprovedLINEA. Bahour9/26/201411/25/2014Springfield Memorial Gardens
15.0150ApprovedREHABA. Bahour3/12/20153/30/201522015 Central Basins Rehabilitation - Phase 3A - Basins 7 & 10