Permit Information

TN0020753
Individual
Reissuance
Town of Huntsville
Huntsville STP
Treatment of municipal sewage by activated sludge process with UV disinfection
I
M
MW
31-AUG-2023
03-OCT-2018
13-SEP-2023
23-JAN-2024
26-FEB-2024
01-APR-2024
31-MAR-2029
New River at mile 14.8
treated municipal wastewater from Outfall 001
Activated Sludge plant with UV Disinfection
4952
.3
08-JUL-2024 03:41PM

Other DWR permits at this site

Permit Documents

View
ReportREF 01-JAN-76: report re: discharge measuremetns at gaging stations by Thomas Buchanan and William Somers.01-JAN-1976
ReportREF 08-JUN-82: report re: Scott High School, TN0030180, proposed standards by Hari Akunuri.08-JUN-1982
ReportREF 24-JAN-84: report re: wasteload allocation by Susan Primm.24-JAN-1984
LetterREF 16-DEC-86: letter re: wasteload allocations by Philip Varsatz.16-DEC-1986
LetterREF 16-FEB-87: letter re: wasteload allocations by James Greenfield.16-FEB-1987
ReportREF 24-AUG-89: report re: 3Q20 by Robert Slayden.24-AUG-1989
MemoREF 08-SEP-89: memo re: modeling for Huntsville permit limits by Robert Slayden.08-SEP-1989
LetterREF 08-SEP-89: letter re: Huntsville Permit Limits by Robert Slayden.08-SEP-1989
LetterREF 02-OCT-90: letter re: recording gages by Charles Gamble.02-OCT-1990
ReportREF 22-DEC-98: report re: planning limits worksheet by Woody Smith.22-DEC-1998
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

OverflowsEFO CommunicationAs of CEI Sept 30, 2019. Moratorium at Express Mart pump station which as the last pump prior to the plant effectively becomes a system wide moratorium.10/7/2019Active

Inspections

02-JUL-2024Compliance Eval (non-sampling) (CEI)In Compliance
26-SEP-2022Compliance Eval (non-sampling) (CEI)In Compliance
05-SEP-2019Compliance Eval (non-sampling) (CEI)Out of Compliance
12-AUG-2019Sanitary Sewer SystemOut of Compliance
22-SEP-2017Compliance Eval (non-sampling) (CEI)Out of Compliance
09-SEP-2015Pretreatment Follow-upIn Compliance
10-JUN-2014Compliance Eval (non-sampling) (CEI)Notice of Deficiency
28-JUN-2012Compliance Eval (non-sampling) (CEI)Follow-up Inspection Required
02-JUN-2010Compliance Eval (non-sampling) (CEI)Notice of Deficiency
28-MAR-2007Compliance Eval (non-sampling) (CEI)In Compliance

Wastewater Engineering Plans Review

24.0596ApprovedCDTNH9/3/20249/3/2024Town of Huntsville Wastewater Treatment Plant Improvements Project
23.0323RApprovedCDTNH3/25/20243/26/2024Town of Huntsville Sewer System Improvements Project: Scenic Hills Pump Station
24.0079Review CompletePERTNH1/31/20241/31/20242021 CDBG Town of Huntsville Sewer System Rehabilitation and Replacement
23.0664Review CompletePERTNH10/17/202311/15/2023Town of Huntsville Sewer System Improvements Project Swifton Village and Scenic Hills Pump Station & Force Main Replacement
23.0323ApprovedCDTNH6/20/202311/28/2023Town of Huntsville Sewer System Improvements Project Swifton Village and Scenic Hills Pump Station & Force Main Replacement
23.0050ApprovedCDA. Bahour2/23/20232/23/20232021 CDBG Town of Huntsville Sewer System Rehabilitation and Replacement
21.0055ApprovedCDTNH3/12/20213/23/2021Town of Huntsville Pump Station Replacement
20.0217ApprovedCDMNU3/30/20204/27/2020Huntsville 2019 CDBG Sewer System Replacement Rehabilitation
16.0523Approved-Sou. Fathi7/6/20167/26/2016WWTP
13.0101RApproved-Phil Simmo9/16/201312/5/2013Wastewater Treatment Plant Upgrade