Skip to Main Content

Parent Site

Site IDSiteLocationCityCountyEFO Name
107211Bean Station Town Property785-821 main streetBean StationGraingerKnoxville

Permit Information

SOP-23005
SOP
New
Town of Bean Station
Municipal Satellite Collection System to Morristown
Operation of a municipal collection system inside the town limits. Phase 1 sewer will serve the corridor of US 25E from the Olen R. Marshall Bridge approximately 1.6 miles north to Crosby Road/Park Drive/Turtle Rock RV Park via: 1) a low pressure sanitary sewer system (LPSS) to serve 120 residential and commercial areas on the east side of US 25E; 2) a municipal lift station pumping southward to Morristown Utility Commission’s sewer system through a 4-inch HDPE force main. Future phases will extend service in the town primarily via LPSS.
N/A
M
CS
01-MAY-2024
12-JUL-2023
21-MAY-2024
28-MAY-2024
05-JUL-2024
01-AUG-2024
31-JUL-2029
Cherokee Lake, 8,000’ (initial distance pump to MH)
05-JUL-2024 02:26PM

Other DWR permits at this site

No other permits found.

Permit Documents

View
PermitNew permit issuance for satellite collection system to Morristown05-JUL-2024
ImagePhotos of Public Notice Sign in View of Public Roadway in Vicinity of the Proposed Activity05-JUN-2024
Draft Permitdraft permit for proposed new satellite collection system24-MAY-2024
LetterWPN23.0119 PER ESU Acceptance Letter 2024052123-MAY-2024
LetterNotice of Complete Application and Public Notice Sign Posting Requirements22-MAY-2024
ApplicationUpdate on TBOUR Approval and Submission of 4th Revision PER to match scope of work01-MAY-2024
LetterReceipt acknowledgement of supplemental SOP application and PER information and notification that application completeness is dependent on Bean Station being in good standing with the TBOR.12-JUL-2023
ApplicationAmendments to SOP and PER16-JUN-2023
LetterSecond Notice of Incomplete Application (Following Review of Supplemental Information)08-JUN-2023
ApplicationResponse to Incomplete Application Letter11-MAY-2023
Forms submitted through MyTDEC Forms after 11/17/2020 will be available in FileNet.

Moratorium

no data found

Inspections

no data found

Wastewater Engineering Plans Review

23.0058IncompleteCDTNH10/11/2023-Town of Bean Station Phase I Sanitary Sewer Line Extension
23.0119Review CompletePERTNH5/1/20245/22/2024Town of Bean Station SOP
22.0376Review CompletePPDTNH6/7/20226/13/2022Town of Bean Station Collection System SOP