Skip to Main Content
Site IDParent SiteLocationCountyEFO
165041River Gorge Ranch (aka Aetna Mtn)195 Whiteside LoopMarionChattanooga

Inspection Details

116134
165041
TNR113978
12/6/2024
Stormwater Construction Non-Sampling
In Compliance
dry weather conditions – no recent rain.
Basins are being installed as phased work progresses; most of current work in phase 1B involves reworking existing roads and cutting new; EPSC maintenance needed in a few locations - discussed during inspection; basin P24 east of easement needs to be installed as work progresses in that area; excavation of Whispering Way in progress – outfall below maintained; did not observe sediment loss; will f/u as needed while phase progresses; 4 stream crossing have been installed – final stabilized needed.