Skip to Main Content
DataViewer - Division of Water Resources (DWR)
Page Help
GUEST
---
Go to Home Page
Home
Permits
Permits on Public Notice
Permits on Public Notice (Map)
Moratoriums
Permit Types
Permitting Actions
Permit Appeals
Documents
Complaints
Inspections
Engineering Plans
Sewage Works
Public Water Systems
Hydrologic Determinations
Exceptional Waters
Ambient Monitoring
Ambient Monitoring Stations
Surface Waters Chemical Data
Tissue Monitoring Data
Habitat Assessments
SQSH Data
QLP Data
Oil & Gas Wells
Water Wells
Licensed Drillers
Driller Report
Notices of Intent
Certified Operators
Septic Systems
Active Pumpers and Installers
Home
DWR Inspections
Inspection Details
Site ID
Parent Site
Location
County
EFO
4919
Clarksville Gas and Water dba Clarksville Wastewater Treatment Plant
15 Quarry Road
Montgomery
Nashville
Inspection Details
Inspection Number
113512
Site ID
4919
Permit Number
TN0020656
Inspection date
7/25/2023
Inspection type
Compliance Eval (non-sampling) (CEI)
Status
In Compliance
Notes
Active construction of the facility’s thermal dryer improvements was ongoing during the inspection. The flood control structures that contributed to the July 12, 2021, illicit discharge and Notice of Violation (NOV) were still locked, with equipment and procedures accessing the sluice gates were still inaccessible and effective, respectively. Two of the three primary clarifiers were in operation during the inspection. One of the three aerobic basins was offline for diffuser improvements. Small amounts of solids were observed leaving the secondary clarifier weirs but did not appear to impact downstream treatment.
Outfall 001 is located about a mile from the facility in the adjacent Riverside Greenway. The effluent contributed fine bubbles to the surface of the receiving stream but did not appear to have any impact on the receiving waters. No odors, scum, or foam were discovered from the outfall during the inspection. Analysis for CBOD, ammonia, TSS, total chlorine residual, E. coli, settleable solids (SS), and dissolved oxygen (DO) are performed in house. Total nitrogen, total phosphorus, and IC25 are contracted out to Pace Analytical.
Clarksville STP is well operated and maintained. No major concerns were noted during the inspection, and the facility appears to be operating in a manner that is compliant with the terms of its NPDES Permit; and continued system upgrades are having a meaningful impact in reducing overflows in the system.