5005Rogersville STP620 Flora LaneHawkinsJohnson City

Inspection Details

106683
5005
TN0020672
2/28/2022
Follow-up
In Compliance
Follow up inspection to document progress on construction project (Wastewater Project Number 20.0293 - Installation of 2 4MGD mechanically cleaned influent screens, concrete structure, and appurtenances). Concrete has been poured, gates are in (being manually operated), and influent flow meter was in operation at time of inspection. Mechanical screens are on-site, but not yet installed. Rogersville is waiting on Holston Electric to install electric and control box. Town of Rogersville Maintenance Dept. is performing all construction work. Rogersville staff stated they expect the project to be complete by April 2022.

Laboratory bench sheets were also reviewed, advised that the Temperature SM 2550B editorial revision date needed to be updated. TRC QA/QC and TSS MDL Blank procedures were discussed along with the MDL calculator. I advised them that they will need to begin maintaining control charts, advised on the location of example control chart spreadsheets available on the FTC website, and suggested they begin with TSS.