Skip to Main Content
Site IDParent SiteLocationCountyEFO
14886Town of Arlington Wastewater Treatment PlantNorth of CSX Railroad, West of Hwy 385, South of the Loosahatchie RiverShelbyMemphis

Inspection Details

73929
14886
TN0078603
8/8/2019
Compliance Assistance
Immediately Corrected During Inspection
Gil Rivera, WWTP Manager, contacted the MEFO regarding a power failure at the plant, the night of 8-7/8-2019, causing approximately 650,000 gallons to overflow onto the ground and adjacent grassy area. The overflow was contained onsite and no Waters of the State were involved. The power failure caused the SCADA system and the PLC system that operates the plant to fail. The power was restored the morning of 8-8-2019. EKB visited the plant on 8-8-2019. The overflow was mitigated by plant personnel and that the plant was back in operation.