Skip to Main Content
DataViewer - Division of Water Resources (DWR)
Page Help
GUEST
---
Go to Home Page
Home
Permits
Permits on Public Notice
Permits on Public Notice (Map)
Moratoriums
Permit Types
Permitting Actions
Permit Appeals
Documents
Complaints
Inspections
Engineering Plans
Sewage Works
Public Water Systems
Hydrologic Determinations
Exceptional Waters
Ambient Monitoring
Ambient Monitoring Stations
Surface Waters Chemical Data
Tissue Monitoring Data
Habitat Assessments
SQSH Data
QLP Data
Oil & Gas Wells
Water Wells
Licensed Drillers
Driller Report
Notices of Intent
Certified Operators
Septic Systems
Active Pumpers and Installers
Home
DWR Inspections
Inspection Details
Site ID
Parent Site
Location
County
EFO
5512
Pine Grove Mobile Home Park
73 Jane Drive
Tipton
Memphis
Inspection Details
Inspection Number
75232
Site ID
5512
Permit Number
SOP-11012
Inspection date
2/25/2020
Inspection type
Compliance Evaluations (non-NPDES)
Status
Out of Compliance
Notes
A written plan describing how rainfall and other surface runoff reaching the pond will be disposed of without discharge has not been developed. Part I of the permit requires that this plan be developed and retained on-site.
The treatment system is not being inspected by a certified operator. Part I of the permit requires the site be inspected by a certified operator or their designee at least once every 14 days.
The waste treatment facility is not being operated under the supervision of a certified wastewater operator and the collection system is not supervised by a grade I certified collection system operator. Part III, Section A of the permit requires the wastewater treatment facility be operated under the supervision of a Biological Natural System certified wastewater treatment operator and the collection system be operated under the supervision of a grade I certified collection system operator.
The appropriate signs were not posted at regular intervals (at least every 150 ft.) around the perimeter of the wastewater treatment lagoon or at the entrance. See Part III, Section B of the permit for additional information.
An area of erosion on the northern portion of the bank of the wastewater treatment lagoon was observed during the inspection.
It should be noted that these are the same deficiencies that were observed during the previous inspection conducted in August 2015.