Site IDParent SiteLocationCountyEFO
5174Manchester Water and Sewer Department736 West High StreetCoffeeColumbia

Inspection Details

17849
5174
TN0025038
12/17/2008
Pretreatment TAV and File Review
In Compliance
No pretreatment issues were identified.

Paul, Jim and DAL did discuss manhole overflows and the City's plans to address the most frequently reported manhole overflows. Manchester has two projects to complete by the end of 2009 that should help. Paul Coston and DAL visited most of these manhole problem sites on 12/17/08.