    Complaint

    132921
    WPC
    7/25/2024
    Other Agency
    Stormwater - Construction
    7/25/2024
    04-AUG-2024 08:11PM

    Location based on SITE_ID

    Site ID
    34593
    Site
    The Orchard
    Location
    Grand View Drive
    City
    Cleveland
    Description
    Subdivision development
    County
    Bradley
    EFO Name
    Chattanooga
    Site Owner
    Rob Renner

    Investigation Results

    NOV
    8/2/2024
    8/2/2024

    Complaint Description and Writeup

    From Bradley County, the portion of the site with issues is parcel # 057 010.00. It does not have any EPSC’s in place, has not been stabilized, has no construction entrance, and is causing significant issues with the catch basins as they are filling up with sediment. It appears that the contractor may have stopped construction prior to Phase II. I have included a screenshot from our GIS for you. The main road leading to the Phase II portion of the site is Courtland Crest Drive SW.

    There is some runoff from the construction entrance. We can send an NOV requesting that the CE be stabilized.