Hydrologic Determination

23-OCT-2024
Virginia Lawrence
Morgan Bishop
KandS Mine Dennie Barber Pit
McNairy
Dennie Barber Road
Clear Creek
4
All the ponds, PND-5, PND-6, and PND-7, were constructed for agricultural purposes and appear to be of low aquatic resource value. Dustin Tucker noted in the submitted report that the origin of STR-1 was difficult to ascertain due to drought conditions during field data collection. Division staff identified the origin and confirmed jurisdictional status (stream) of STR-1 during the ground truth site visit.
approximately 7 days no rain ~ 0.0 (9-10-24)
dry
16-SEP-2024
23-OCT-2024
Permittee
No
24-OCT-2024
Yes
35.161558
-88.392929

Determination Documents

ViewAuthorFile typeMailed date
VDLImage10/24/2024
VDLLetter10/24/2024
Dustin Tucker Report9/16/2024