Skip to Main Content
  • Engineering Plan Details

Engineering Plan Details

21.0215
Sewer
Review Complete
Munford Lagoon Upgrade
PPD
Preliminary Project Discussion
TFMOD
Treatment Facility upgrade or modification
Munford
TN0062499
3/11/2021
3/25/2021
King Engineering Consultants
Email
TNH
Tim Hill, P.E.
(865) 364-9535
Timothy.Hill@tn.gov

Associated Engineering Documents

View
Letter21.0215 Background Information for PPD11-MAR-2021TN0062499
Image21.0215 Map of Property05-APR-2021TN0062499
Letter21.0215 Request for variance to design criteria05-APR-2021TN0062499
Memo21.0215 Munford Lagoon Upgrade PPD 3-25-21 (1)06-APR-2021TN0062499

Associated Permit

TN0062499City of MunfordMunford Sewer Department LagoonIndividualModificationMajor8/14/20249/1/202412/31/2025