Skip to Main Content
  • Engineering Plan Details

Engineering Plan Details

15.0314
Sewer
Review Complete
Plant Expansion
ER
Engineering Report (if submitted in final step)
ER
Engineering Report (if submitted in final step)
Decatur - Town
TN0058521
5/18/2015
Stantec Consulting Services, Inc.
SEF
Souraya Fathi
(615) 981-5531
Souraya.Fathi@tn.gov

Associated Engineering Documents

View
Engineering SpecificationsWPN15-0314 REF 28-JUL-15: eng spec re: wastewater treatment plant improvements 2015, Stantec Project# 175618302, by Paul Thomas, Tyler Marshall & Aaron Wilburn of Stantec.28-JUL-2015TN0058521
ReportEngineering Report for Plant Expansion Design Verification WPN15-031418-MAY-2015TN0058521

Associated Permit